ER26-3515-000 · 2026-09-03 · Sierra Club, Natural Resources Defense Council and 3 others

Limited Protest of Public Interest Organizations requesting narrow modifications of the proposed Interim Resource Adequacy Service by PJM Interconnection, L.L.C

Text extracted from the eLibrary original (SHA-256 59e27b263e9e2f37…). Download the original from the official source.

Contents · 51 sections
  1. I. PJM is facing resource adequacy and affordability concerns as it struggles to meet data p. 3
  2. A. PJM’s capacity market faces increased reliability risks as data center load grows p. 3
  3. B. PJM’s supply and demand imbalance is causing high capacity prices, leading to p. 3
  4. II. The Commission should accept PJM’s Interim Resource Adequacy Service and Large p. 3
  5. C. Removing New Large Loads from RPM is just, reasonable, and not unduly p. 3
  6. II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish PJM’s p. 3
  7. A. Objective One: Promote Reliability by Requiring New Large Loads to be Curtailable p. 3
  8. B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay for p. 3
  9. C. Objective Three: Provide States and LSEs With Sufficient Information to Ensure the p. 3
  10. III. Modification 1: The Commission must ensure that the IRAS filing effectively removes p. 3
  11. A. Suspending the IRAS Framework during periods of resource adequacy risks pinning p. 3
  12. B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and p. 3
  13. C. The Commission should modify PJM’s IRAS Filing to make the IRAS Framework p. 4
  14. IV. Modification 2: The Commission Should Modify the IRAS Filing to Include Penalties p. 4
  15. A. Commission Precedent Supports Operational and Financial Consequences When a p. 4
  16. C. If the Commission declines to impose operational penalties, then the Commission p. 4
  17. V. Modification 3: The Commission Should Reject IRAS Compensation or, in the p. 4
  18. A. Curtailability Is a Condition of Speed to Power, Not a Separately Compensable p. 4
  19. C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-Emergency p. 4
  20. D. The Commission Should Remove IRAS Performance Compensation or, in the p. 4
  21. VI. Modification 4: The Commission should require BYONC supply to be fully deliverable p. 4
  22. INTRODUCTION p. 5
  23. BACKGROUND p. 9
  24. I. PJM is facing resource adequacy and affordability concerns as it struggles to meet p. 9
  25. A. PJM’s capacity market faces increased reliability risks as data center load p. 10
  26. B. PJM’s supply and demand imbalance is causing high capacity prices, leading p. 13
  27. II. The Commission should accept PJM’s Interim Resource Adequacy Service and p. 15
  28. DISCUSSION p. 16
  29. I. The IRAS Framework is just and reasonable and not unduly discriminatory. p. 16
  30. A. Large load customers are differently situated from other customers. p. 17
  31. B. IRAS is jurisdictionally sound and respects the roles of states and PJM. p. 22
  32. C. Removing New Large Loads from RPM is just, reasonable, and not unduly p. 24
  33. II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish p. 27
  34. A. Objective One: Promote Reliability by Requiring New Large Loads to be p. 28
  35. B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay p. 30
  36. C. Objective Three: Provide States and LSEs With Sufficient Information to p. 32
  37. III. Modification 1: The Commission must ensure that the IRAS filing effectively p. 34
  38. A. Suspending the IRAS Framework during periods of resource adequacy risks p. 35
  39. B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and p. 38
  40. C. The Commission should modify PJM’s IRAS Filing to make the IRAS p. 40
  41. IV. Modification 2: The Commission Should Modify the IRAS Filing to Include p. 42
  42. A. Commission Precedent Supports Operational and Financial Consequences p. 43
  43. B. The Commission Should Require Operational Penalties for Failure to p. 44
  44. C. If the Commission declines to impose operational penalties, then the p. 48
  45. V. Modification 3: The Commission Should Reject IRAS Compensation or, in the p. 50
  46. A. Curtailability Is a Condition of Speed to Power, Not a Separately p. 51
  47. B. Cost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge p. 53
  48. C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre- p. 54
  49. D. The Commission Should Remove IRAS Performance Compensation or, in p. 55
  50. VI. Modification 4: The Commission should require BYONC supply to be fully p. 56
  51. CONCLUSION p. 60

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

PIOs believe the IRAS Filing could, if modified as described below, permanently resolve emerging resource adequacy shortfalls while respecting jurisdictional boundaries.
Read this passage Filed comments: Reliability and curtailment

TABLE OF CONTENTS

printed heading

TABLE OF CONTENTS INTRODUCTION .......................................................................................................................... 1 BACKGROUND ............................................................................................................................ 5
Read this passage

I. PJM is facing resource adequacy and affordability concerns as it struggles to meet data

printed heading · Topic match: Reliability and curtailment

I.
Read this passage Filed comments: Reliability and curtailment

A. PJM’s capacity market faces increased reliability risks as data center load grows

printed heading

A.
Read this passage

B. PJM’s supply and demand imbalance is causing high capacity prices, leading to

printed heading · Topic match: Cost allocation

B.
Read this passage Filed comments: Cost allocation

II. The Commission should accept PJM’s Interim Resource Adequacy Service and Large

printed heading · Topic match: Registry access

II.
Read this passage Filed comments: Registry access

C. Removing New Large Loads from RPM is just, reasonable, and not unduly

printed heading

C.
Read this passage

II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish PJM’s

printed heading

II.
Read this passage

A. Objective One: Promote Reliability by Requiring New Large Loads to be Curtailable

printed heading

A.
Read this passage

B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay for

printed heading · Topic match: Cost allocation

B.
Read this passage Filed comments: Cost allocation

C. Objective Three: Provide States and LSEs With Sufficient Information to Ensure the

printed heading

C.
Read this passage

III. Modification 1: The Commission must ensure that the IRAS filing effectively removes

printed heading

Modification 1: The Commission must ensure that the IRAS filing effectively removes new large loads from the capacity market until associated new capacity is online and deliverable.…
Read this passage

A. Suspending the IRAS Framework during periods of resource adequacy risks pinning

printed heading · Topic match: Reliability and curtailment

A.
Read this passage Filed comments: Reliability and curtailment

B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and

printed heading

B.
Read this passage

C. The Commission should modify PJM’s IRAS Filing to make the IRAS Framework

printed heading

C.
Read this passage

IV. Modification 2: The Commission Should Modify the IRAS Filing to Include Penalties

printed heading

IV.
Read this passage

A. Commission Precedent Supports Operational and Financial Consequences When a

printed heading

A.
Read this passage

C. If the Commission declines to impose operational penalties, then the Commission

printed heading

C.
Read this passage

V. Modification 3: The Commission Should Reject IRAS Compensation or, in the

printed heading

V.
Read this passage

A. Curtailability Is a Condition of Speed to Power, Not a Separately Compensable

printed heading · Topic match: Cost allocation

Cost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge Credit. 49
Read this passage Filed comments: Cost allocation

C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-Emergency

printed heading

C.
Read this passage

D. The Commission Should Remove IRAS Performance Compensation or, in the

printed heading

D.
Read this passage

VI. Modification 4: The Commission should require BYONC supply to be fully deliverable

printed heading

VI.
Read this passage

INTRODUCTION

printed heading · Topic match: Cost allocation

PJM is proposing changes that generally support the Statement of Principles Regarding PJM issued on January 16, 2026, by the National Energy Dominance Council and the 13 governors of the PJM States,10 the Ratepayer Protection Pledge signed by more than 200 utilities, developers, cooperatives, and…
Read this passage Filed comments: Cost allocation

BACKGROUND

printed heading

BACKGROUND
Read this passage

I. PJM is facing resource adequacy and affordability concerns as it struggles to meet

printed heading · Topic match: Reliability and curtailment

PJM is facing resource adequacy and affordability concerns as it struggles to meet data center load growth.
Read this passage Filed comments: Reliability and curtailment

A. PJM’s capacity market faces increased reliability risks as data center load

printed heading

For Science and Int’l Aff. (Apr. 20, 2026), https://www.belfercenter.org/research-analysis/data-centers-texas-virginia-comparison. 30 Id. 31 IRAS Filing, supra note 2, at 14. 32 PJM Auction Procures 134,479 MW of Generation Resources, PJM Inside Lines (Dec. 1, 2025)…
Read this passage

B. PJM’s supply and demand imbalance is causing high capacity prices, leading

printed heading · Topic match: Cost allocation

PJM’s supply and demand imbalance is causing high capacity prices, leading to historically high bills for all ratepayers.
Read this passage Filed comments: Cost allocation

II. The Commission should accept PJM’s Interim Resource Adequacy Service and

printed heading · Topic match: Reliability and curtailment

The Commission should accept PJM’s Interim Resource Adequacy Service and Large Load Registry with modifications to better achieve the IRAS’s objectives.
Read this passage Filed comments: Reliability and curtailment

DISCUSSION

printed heading

DISCUSSION
Read this passage

I. The IRAS Framework is just and reasonable and not unduly discriminatory.

printed heading · Topic match: Registry access

PJM proposed to establish a Large Load Registry, require LSEs to ensure that New Large Loads BYONC, implement IRAS load reduction requests prior to Pre-Emergency Load Management Response, and remove New Large Loads that do not BYONC from the VRR Curve in the capacity auction.
Read this passage Filed comments: Registry access

A. Large load customers are differently situated from other customers.

printed heading · Topic match: Reliability and curtailment

The North American Electric Reliability Corporation (“NERC”) documented that data center facilities pose an unprecedented reliability threat: they can instantly trip over 1,000 MW of power offline simultaneously, without time for RTOs or 53 Monitoring Analytics Q2 Report, supra note 51, at 17, tbl.…
Read this passage Filed comments: Reliability and curtailment

B. IRAS is jurisdictionally sound and respects the roles of states and PJM.

printed heading · Topic match: Registry access

PJM proposes new rules that directly affect wholesale market prices and grid reliability.
Read this passage Filed comments: Registry access

C. Removing New Large Loads from RPM is just, reasonable, and not unduly

printed heading · Topic match: Cost allocation

Removing new large loads that do not BYONC from the VRR Curve observes principles of cost causation because it prevents the RPM from forcing other ratepayers to subsidize capacity on behalf of new large loads.
Read this passage Filed comments: Cost allocation

II. The Commission Should Only Modify PJM’s IRAS Filing to Better Accomplish

printed heading · Topic match: Cost allocation

PJM describes the “foundation” of IRAS as the rule that large loads (through their LSEs) must bring new capacity in an amount equal to or greater than their contribution to peak demand, or else the load may be reduced during emergency conditions.77 Second, promote affordability by requiring large…
Read this passage Filed comments: Cost allocation

A. Objective One: Promote Reliability by Requiring New Large Loads to be

printed heading · Topic match: Reliability and curtailment

A new large load may interconnect before sufficient new capacity is in place, but the unmatched load must remain available for reduction 78 Id. at 4–5. 79 Id. at 5–7. 80 Id. at 13–15, 21; see also id. at Attach.
Read this passage Filed comments: Reliability and curtailment

B. Objective Two: Promote Affordability by Requiring New Large Loads to Pay

printed heading · Topic match: Cost allocation

FERC, 373 F.3d at 1368. 86 IRAS Filing, supra note 2, at 5 (quoting White House Ratepayer Protection Pledge). 27 impacts” of procuring new capacity for them.87 PJM also states that the IRAS Filing’s interlocking components are designed to induce new large loads to meet their capacity needs while…
Read this passage Filed comments: Cost allocation

C. Objective Three: Provide States and LSEs With Sufficient Information to

printed heading · Topic match: Registry access

It says the Large Load Registry will facilitate “transparent implementation of IRAS” and help states monitor whether data centers and other large loads are honoring their commitment to provide for their own 92 Id. at 3. 93 Id. at 6. 94 Id. at 3. 95 Id. at Pilong Aff. ¶ 52; see also id. at 82 nn.…
Read this passage Filed comments: Registry access

III. Modification 1: The Commission must ensure that the IRAS filing effectively

printed heading · Topic match: Reliability and curtailment

Modification 1: The Commission must ensure that the IRAS filing effectively removes new large loads from the capacity market until associated new capacity is online and deliverable.
Read this passage Filed comments: Reliability and curtailment

A. Suspending the IRAS Framework during periods of resource adequacy risks

printed heading · Topic match: Reliability and curtailment

However, because PJM proposes to remove New Large Loads from the VRR Curve and the Reliability Requirement, the capacity market merely satisfying that lowered Reliability Requirement is not an appropriate trigger for suspending the IRAS Framework.
Read this passage Filed comments: Reliability and curtailment

B. PJM’s proposal to toggle IRAS on and off creates regulatory uncertainty and

printed heading · Topic match: Reliability and curtailment

These impacts hold true regardless of PJM’s resource adequacy situation.
Read this passage Filed comments: Reliability and curtailment

C. The Commission should modify PJM’s IRAS Filing to make the IRAS

printed heading · Topic match: Reliability and curtailment

Either way, PJM must close this loophole that could pin prices at the cap, harm other customers, and produce a volatile market with constantly changing expectations.
Read this passage Filed comments: Reliability and curtailment

IV. Modification 2: The Commission Should Modify the IRAS Filing to Include

printed heading · Topic match: Reliability and curtailment

Modification 2: The Commission Should Modify the IRAS Filing to Include Penalties When Eligible New Large Loads Fails to Curtail With the IRAS Framework, PJM permits new large loads to obtain “speed to power” before bringing sufficient capacity online.110 In exchange, the unmatched portion of that…
Read this passage Filed comments: Reliability and curtailment

A. Commission Precedent Supports Operational and Financial Consequences

printed heading · Topic match: Reliability and curtailment

In exchange, the load must remain available for curtailment.
Read this passage Filed comments: Reliability and curtailment

B. The Commission Should Require Operational Penalties for Failure to

printed heading · Topic match: Reliability and curtailment

A data center’s RAS misoperation or failure to comply with curtailment directives could have serious consequences, including the loss of all interim or non-firm load in one area—or even cascading outages across the Eastern Interconnection.121 PJM found that strict penalties were needed to mitigate…
Read this passage Filed comments: Reliability and curtailment

C. If the Commission declines to impose operational penalties, then the

printed heading · Topic match: Reliability and curtailment

An effective financial penalty must be more than merely the cost of doing business for wealthy large loads.
Read this passage Filed comments: Reliability and curtailment

V. Modification 3: The Commission Should Reject IRAS Compensation or, in the

printed heading · Topic match: Reliability and curtailment

Required IRAS curtailment is the condition on which unmatched large loads receive accelerated service, not an independently procured product for which other customers should pay.
Read this passage Filed comments: Reliability and curtailment

A. Curtailability Is a Condition of Speed to Power, Not a Separately

printed heading · Topic match: Reliability and curtailment

An Eligible New Large Load does not provide IRAS curtailment as an independently procured capacity or demand-response resource.
Read this passage Filed comments: Reliability and curtailment

B. Cost Causation Principles Support a Zero-Dollar Rate or a Capacity-Charge

printed heading · Topic match: Reliability and curtailment

Rates must be roughly commensurate with the costs imposed or the benefits received by any given ratepayer.141 PJM’s proposed default rate does not satisfy that standard.
Read this passage Filed comments: Reliability and curtailment

C. PJM’s Reliance on the Commission’s Decision on Compensation for Pre-

printed heading

PJM’s Reliance on the Commission’s Decision on Compensation for Pre- Emergency Load Response Does Not Justify the Proposed Rate.
Read this passage

D. The Commission Should Remove IRAS Performance Compensation or, in

printed heading · Topic match: Cost allocation

It provides unnecessary payments to Eligible New Large Loads that are already compensated by their speed to power and funds those payments through charges to existing ratepayers who derive no benefit. 145 Co-Location Order, 193 FERC ¶ 61,217, at P 5. 146 Id. 147 Id. at PP 5, 529. 148 IRAS Filing,…
Read this passage Filed comments: Cost allocation

VI. Modification 4: The Commission should require BYONC supply to be fully

printed heading · Topic match: Cost allocation

The Commission should direct PJM to require BYONC to be located only in zones that are not constrained with respect to the zone in which the new large load resides. 149 See, e.g., PJM Interconnection, L.L.C., 117 FERC 61,331, at P 48 (2006) (approving the settlement establishing the basic structure…
Read this passage Filed comments: Cost allocation

CONCLUSION

printed heading · Topic match: Reliability and curtailment

However, to ensure that the IRAS Filing achieves its objectives, the Commission must make the modifications described above to: (1) ensure IRAS and BYONC requirements are permanent for all new large loads or else clarify that the trigger for turning IRAS off requires the capacity market to clear…
Read this passage Filed comments: Reliability and curtailment