Supportive Comments and Limited Protest of the New Jersey Board of Public Utilities re PJM Interconnection, L.L.C.’s filing to establish Interim Resource…
Text extracted from the eLibrary original (SHA-256 1c850a066b8233a5…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
ER26-3515-000 SUPPORTIVE COMMENTS AND LIMITED PROTEST OF THE NEW JERSEY BOARD OF PUBLIC UTILITIES On August 13, 2026, PJM Interconnection, L.L.C. (“PJM”) proposed revisions to the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) and the PJM Open Access Transmission Tariff…Read this passage Filed comments: Reliability and curtailment
I. Background
printed heading · Topic match: Reliability and curtailment
For the first time in history, PJM’s Base Residual Auction (“BRA”) for the 2027/2028 Delivery Year (“DY”) cleared short of 1 PJM Interconnection, L.L.C., Proposal to Establish Interim Resource Adequacy Service and a Large Load Registry to Address System Reliability, Docket No.Read this passage Filed comments: Reliability and curtailment
II. Interim Resource Adequacy Service
printed heading · Topic match: Reliability and curtailment
The Board also requests clarification regarding the interaction between the three-year shortfall condition and PJM’s proposed exclusion of New Large Load amounts from the VRR Curve.Read this passage Filed comments: Reliability and curtailment
III. Large Load Registry
printed heading · Topic match: Registry access
Large Load Registry The Board supports the proposed Large Load Registry and appreciates PJM’s role in leading the development and maintenance of such registry.Read this passage Filed comments: Registry access
IV. Removal of Demand from VRR Curve
printed heading · Topic match: Cost allocation
Additionally, keeping 27 Letter from Christine Guhl-Sadovy, President, New Jersey Board of Public Utilities, to the PJM Board of Managers (Mar. 27, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260401-njbpu-letter-re-connect-and-manage-issue-charge.pdf.…Read this passage Filed comments: Cost allocation
V. Conclusion
printed heading · Topic match: Cost allocation
However, the Board’s support does not come without concerns, and the Board requests that certain elements of the Proposal are 17 severed where doing so would better uphold the Ratepayer Protection Pledge without significantly affecting the Proposal’s core components.Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
By: /s/ Steven Chaplar Steven Chaplar Deputy Attorney General New Jersey Office of the Attorney General Department of Law & Public Safety P.O.Read this passage