ER26-3515-000 · 2026-09-03 · American Municipal Power, Inc.

Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026

Text extracted from the eLibrary original (SHA-256 0394c9aaaefc0f0f…). Download the original from the official source.

Contents · 6 sections
  1. I. INTRODUCTION p. 1
  2. II. LIMITED PROTEST p. 4
  3. A. PJM’s proposal to fix the Accredited UCAP of BYONC without p. 4
  4. B. PJM has not established that the proposed treatment of BYONC in the p. 6
  5. C. The Commission should direct PJM to modify its proposal for p. 9
  6. III. CONCLUSION p. 10

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 American Municipal Power, Inc. (“AMP”) submits this limited protest of the August 13, 2026 filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,2…
Read this passage Filed comments: Reliability and curtailment

I. INTRODUCTION

printed heading · Topic match: Cost allocation

The PJM Filing proposes to establish “Large Load” and “New Large Load” as new defined terms.
Read this passage Filed comments: Cost allocation

II. LIMITED PROTEST

printed heading

II.
Read this passage

A. PJM’s proposal to fix the Accredited UCAP of BYONC without

printed heading · Topic match: Reliability and curtailment

The portion of a New Large Load that exceeds the ELCC-measured UCAP of a supporting BYONC resource is effectively the same as unhedged, Eligible New Large Load, but without the corresponding IRAS load curtailment obligation.
Read this passage Filed comments: Reliability and curtailment

B. PJM has not established that the proposed treatment of BYONC in the

printed heading

BYONC would be required to participate as a price taker in RPM auctions for ten consecutive Delivery Years “to ensure that BYONC clear the auction and obtain a 17 Notably, PJM proposes to require Demand and DER Capacity Aggregation Resources to demonstrate their Accredited UCAP values “each year…
Read this passage

C. The Commission should direct PJM to modify its proposal for

printed heading · Topic match: Cost allocation

Given the potential adverse reliability impacts and cost shifts associated with resources that have declining accreditations over time, however, it is better to err on the side of capturing these projected declines, albeit imprecisely, rather than use PJM’s “set and forget” approach to accrediting…
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. submits its limited protest in this proceeding and asks that the Commission consider it in acting on the PJM Filing.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 3rd day of September, 2026. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.com