ER26-3515-000 · 2026-09-03 · Sunrun Inc.

Motion to Intervene and Comments of Sunrun Inc. in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim Resource Adequacy…

Text extracted from the eLibrary original (SHA-256 d61a398adbf05da0…). Download the original from the official source.

Contents · 9 sections
  1. I. Introduction and Summary p. 2
  2. II. Motion to Intervene p. 3
  3. III. Comments p. 4
  4. A. The Commission Should Ensure That Verified Peak Shaving Adjustments Reduce p. 5
  5. C. Broader Multi-Nodal Aggregation Is Needed for Residential DERs to Support IRAS p. 7
  6. D. PJM Has Outlined Registration Timing, but State and EDC Readiness Requires p. 9
  7. E. Routine Additions and Like-for-Like Substitutions Should Not Restart Full Review p. 10
  8. F. These Reforms Preserve Reliability and Avoid Double Counting While Making p. 11
  9. IV. Conclusion and Prayer for Relief p. 13

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

This filing responds to the proposal by PJM Interconnection, L.L.C. (“PJM”) to establish Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry, filed on August 13, 2026 under Section 205 of the Federal Power Act, 16 U.S.C. section 824d, Accession No. 20260813-5118, with a requested…
Read this passage Filed comments: Registry access

I. Introduction and Summary

printed heading · Topic match: Registry access

PJM requests an effective date of October 12, 2026.
Read this passage Filed comments: Registry access

II. Motion to Intervene

printed heading · Topic match: Reliability and curtailment

PJM’s August 13, 2026 filing in this docket proposes to establish an Interim Resource Adequacy Service (“IRAS”) and a Large Load Registry.
Read this passage Filed comments: Reliability and curtailment

III. Comments

printed heading · Topic match: Registry access

The Commission can and should direct a discrete clarification or compliance filing on that point, consistent with the principle that a utility’s Section 205 filing must be just and reasonable in its own terms.
Read this passage Filed comments: Registry access

A. The Commission Should Ensure That Verified Peak Shaving Adjustments Reduce

printed heading · Topic match: Registry access

A Workable IRAS DER Pathway Requires Separate Treatment of Battery Injections and Net-Metered Solar Exports If DER-backed capacity is to support IRAS compliance, PJM must establish settlement rules that distinguish battery storage injections from net-energy-metered solar exports.
Read this passage Filed comments: Registry access

C. Broader Multi-Nodal Aggregation Is Needed for Residential DERs to Support IRAS

printed heading

To reach capacity levels meaningful for IRAS purposes, an aggregator must enroll hundreds or thousands of customers.
Read this passage

D. PJM Has Outlined Registration Timing, but State and EDC Readiness Requires

printed heading

Sunrun respectfully requests that the Commission, through a technical conference or coordinated follow-up proceeding, address the following measures to ensure accountability: (e)​ Uniform data requirements for EDC submissions and aggregator applications across PJM. (f)​ Transparent status tracking…
Read this passage

E. Routine Additions and Like-for-Like Substitutions Should Not Restart Full Review

printed heading

Sunrun requests that the Commission direct PJM to adopt expedited, ministerial treatment for routine additions and like-for-like substitutions that satisfy each of the following conditions: (j)​ The substitution or addition does not increase the aggregate committed MW of the DER Capacity…
Read this passage

F. These Reforms Preserve Reliability and Avoid Double Counting While Making

printed heading · Topic match: Reliability and curtailment

The safeguards Sunrun proposes operate in concert to protect reliability and prevent double counting: (m)​ Measurement and Verification: PSA offsets and DER capacity contributions would be validated through defined protocols before any IRAS obligation is reduced, ensuring that only demonstrated…
Read this passage Filed comments: Reliability and curtailment

IV. Conclusion and Prayer for Relief

printed heading

Conclusion and Prayer for Relief For the reasons set forth above, Sunrun Inc. respectfully requests that the Commission: (r)​ Grant Sunrun’s motion to intervene in Docket No.
Read this passage

Certificate of Service

printed heading

Certificate of Service
Read this passage

CERTIFICATE OF SERVICE

printed heading

ER26-3515-000, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026). /s/ S.