ER26-3515-000 · 2026-09-03 · Calibrant Energy

Comments of Calibrant Energy requesting clarifications of PJM Interconnection, L.L.C.’s proposal filed on 08/13/2026

Text extracted from the eLibrary original (SHA-256 a84228e4004e6a8e…). Download the original from the official source.

Contents · 4 sections
  1. I. REQUIRED CLARIFICATIONS p. 3
  2. A. Calibrant requests clarification that incremental Demand Resource capacity p. 3
  3. B. Calibrant requests clarification that a New Large Load and BYONC’s p. 8
  4. C. Calibrant requests clarification that a Demand Resource’s 10-year p. 10

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

Calibrant participated in PJM’s stakeholder process to ensure that 1 18 C.F.R. § 385.211. 2 Throughout these comments, Calibrant requests that aspects of PJM’s filing be clarified to address ambiguities in the proposed Tariff and RAA revisions, so as to provide greater clarity to market…
Read this passage Filed comments: Reliability and curtailment

I. REQUIRED CLARIFICATIONS

printed heading

I.
Read this passage

A. Calibrant requests clarification that incremental Demand Resource capacity

printed heading · Topic match: Reliability and curtailment

DD-4 § VI(b)(ii)(1) (pdf page 100) (emphasis added). 6 Calibrant respectfully asks for clarification that this insertion is not intended to prohibit Demand Resources that previously participated in the RPM from providing BYONC by installing reliable, steel-in-the-ground behind-the-meter storage or…
Read this passage Filed comments: Reliability and curtailment

B. Calibrant requests clarification that a New Large Load and BYONC’s

printed heading · Topic match: Reliability and curtailment

Put differently, “once BYONC is in an arrangement with a New Large Load”— and BYONC completes its RPM must-offer obligations under proposed Tariff Attachment DD-4, section VIII, “the New Large Load gets the benefit of ‘bringing’ this new capacity to the system and permanently reduces its…
Read this passage Filed comments: Reliability and curtailment

C. Calibrant requests clarification that a Demand Resource’s 10-year

printed heading

Calibrant requests clarification that a Demand Resource’s 10-year demonstration obligation applies on an ICAP basis and, for New Large Load Demand Resource, does not apply in Year 1.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: September 3, 2026 /s/ Nathan Lobel Nathan Lobel Roselle LLP 300 New Jersey Ave.