Protest of America's Power re PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
Text extracted from the eLibrary original (SHA-256 3200942b73b96345…). Download the original from the official source.
Contents · 7 sections
- I. THE PJM IRAS PROPOSAL
- II. PROTEST
- A. PJM’s IRAS Proposal is Unjust and Unreasonable and Unduly
- B. PJM’s Proposal Results in Price Suppression
- H. Comm. on Energy & Commerce, 119th Cong. (Mar. 25, 2025), https://www.pjm.com/-
- C. PJM’s Proposal Results in a Negative Impact on Reliability
- III. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
ER26-3515-000 ) ) PROTEST OF AMERICA’S POWER Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 America’s Power2 protests the unjust, unreasonable and unduly discriminatory Interim Resource Adequacy Service (“IRAS”) proposal…Read this passage Filed comments: Reliability and curtailment
I. THE PJM IRAS PROPOSAL
printed heading · Topic match: Cost allocation
Page | 4 PJM defines BYONC as a quantity of capacity that permits a New Large Load to satisfy its obligation through contracts with one or more resources.14 The contracted capacity, however, must constitute an actual addition to PJM’s supply.15 Eligible resources may include new generation,…Read this passage Filed comments: Cost allocation
II. PROTEST
printed heading
II.Read this passage
A. PJM’s IRAS Proposal is Unjust and Unreasonable and Unduly
printed heading · Topic match: Reliability and curtailment
Cir. 2022)(finding undue discrimination where threshold “unduly discriminates against small zones, which must absorb higher cost allocations after large zones are exempted.”).Read this passage Filed comments: Reliability and curtailment
B. PJM’s Proposal Results in Price Suppression
printed heading · Topic match: Reliability and curtailment
Although Large Load demand is increasing, PJM proposes to exclude that demand from its capacity forecast.Read this passage Filed comments: Reliability and curtailment
H. Comm. on Energy & Commerce, 119th Cong. (Mar. 25, 2025), https://www.pjm.com/-
printed heading · Topic match: Cost allocation
Page | 15 The recent National Coal Council (“NCC”) report highlights the need to retain existing generation resources such as coal given the rapid demand growth resulting from data centers.38 The NCC Report states: After nearly 15 years of flat electricity demand, the grid must now support rapid…Read this passage Filed comments: Cost allocation
C. PJM’s Proposal Results in a Negative Impact on Reliability
printed heading · Topic match: Reliability and curtailment
Page | 20 them with new capacity, which can take several years to build.”48 Despite this, PJM proposes to exclude existing generation, including coal units, from serving the increasing Large Load demand with no justification.Read this passage Filed comments: Reliability and curtailment
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the reasons explained fully herein, America’s Power requests that the Commission reject PJM’s unjust, unreasonable and unduly discriminatory IRAS Proposal.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 3rd day September, 2026.Read this passage