Protest of the Electric Power Supply Association to PJM Interconnection, L.L.C.’s filing to establish Interim Resource Adequacy Service
Text extracted from the eLibrary original (SHA-256 ede2899f6b17e652…). Download the original from the official source.
Contents · 31 sections
- I. PROTEST
- A. PJM’s BYONC Requirement for New Large Loads is Unduly
- B. The Sotkiewicz Affidavit Identifies Other Unjust, Unreasonable, and
- C. The IRAS Proposal Should be Rejected in Its Entirety
- D. There Are Alternatives Available to PJM and the Commission that
- II. CONCLUSION
- Attachment A
- I. INTRODUCTION AND SUMMARY
- II. QUALIFICATIONS
- III. THE CURRENT RPM CAPACITY MARKET TRADES A FUNGIBLE COMMODITY
- A. Commodity Markets Trade Fungible Commodities
- B. UCAP as a Fungible Commodity
- IV. UNDULY DISCRIMINATORY AND PREFERENTIAL ASPECTS OF IRAS.
- A. Inclusion or Exclusion of Loads from the VRR Curve in the RPM BRAs or IAs
- B. The Offer Requirements into RPM Auctions that Differ Between BYONC, RBP,
- C. Differential Capacity Accreditation Between BYONC Resources and All Other
- D. The Implicit Restrictions on the LSEs and Loads with Whom Existing Capacity
- E. Disparate Treatment of Different Loads by Size and In-Service Date for
- F. Eligible New Large Load Providing IRAS is Compensated and Treated Differently
- Attachment K-Appendix.
- V. IRAS CREATES MULTIPLE UCAP COMMODITIES OUT OF A ONCE FUNGIBLE
- A. UCAP from Existing Capacity Resources
- B. UCAP from BYONC Resources
- VI. IMPLIED PROPERTY RIGHTS CREATED AND GRANTED BY IRAS
- A. Property Rights of Existing Capacity Resources Have Been Reallocated to Existing
- B. Property Rights to Energy In Real-time Operations has Been Assigned to Eligible New
- VII. MARKET
- A. The Incentives Under IRAS Likely Will Not Bring the New Entry that PJM Expects
- B. Existing Capacity Resources Will Have Incentives to Exit the Market if New Entry
- C. New Large Loads Will Have Incentives to Inefficiently Reduce Their Size to Avoid
- VIII. CONCLUSIONS AND A WAY FORWARD BY LEARNING THE LESSONS OF
Read topic-matched comments in ER26-3515
Topics in the text: Cost allocation · Reliability and curtailment · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
Capitalized terms not defined herein have the meaning set forth in the August 13 Filing or, if not therein defined, the Reliability Assurance Agreement Among Load Serving Entities (the “RAA”) and the PJM Open Access Transmission Tariff (the “Tariff”), as applicable. 4 The August 13 Filing also…Read this passage Filed comments: Registry access
I. PROTEST
printed heading
Sotkiewicz, Ph.D., provided as Attachment A hereto (the “Sotkiewicz Affidavit”), the IRAS proposal set forth in the August 13 Filing is unduly discriminatory and preferential and otherwise unlawful and must therefore be rejected in its entirety.Read this passage
A. PJM’s BYONC Requirement for New Large Loads is Unduly
printed heading · Topic match: Cost allocation
See also The White House, President Trump’s Ratepayer Protection Pledge Secures American AI Dominance, Protects Consumers (July 23, 2026), https://www.whitehouse.gov/releases/2026/07/president- trumps-ratepayer-protection-pledge-secures-american-ai-dominance-protects-consumers/. 36 Ratepayer…Read this passage Filed comments: Cost allocation
B. The Sotkiewicz Affidavit Identifies Other Unjust, Unreasonable, and
printed heading · Topic match: Cost allocation
Ratepayers pay theirs. https://www.whitehouse.gov/ratepayer-protection-pledge/ (identifying signatories). 38 See, e.g., August 13 Filing, Transmittal Letter at 23 (stating that IRAS allows PJM to “call[] for load reductions from those New Large Loads that do not adhere to the Ratepayer Protection…Read this passage Filed comments: Cost allocation
C. The IRAS Proposal Should be Rejected in Its Entirety
printed heading · Topic match: Registry access
Cir. 2017) (“NRG-PML”). 56 August 13 Filing, Transmittal Letter at 9. 57 16 U.S.C. § 824d (2024). 58 NRG-PML, 862 F.3d at 110. 15 Section 205, as interpreted in NRG-PML.59 That being the case and given the fatal legal defects in the IRAS proposal described above, the Commission can, should and…Read this passage Filed comments: Registry access
D. There Are Alternatives Available to PJM and the Commission that
printed heading · Topic match: Reliability and curtailment
There Are Alternatives Available to PJM and the Commission that Would Preserve the Integrity of the RPM Construct While Protecting Existing Loads While EPSA appreciates the policy concerns that PJM is attempting to address through the IRAS proposal, it is well-established that “policy interests . .…Read this passage Filed comments: Reliability and curtailment
II. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, EPSA respectfully requests that the Commission reject the August 13 Filing.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 3rd day of September 2026. /s/ David G.Read this passage
Attachment A
printed heading
Attachment A The Sotkiewicz Affidavit UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) Docket No.Read this passage
I. INTRODUCTION AND SUMMARY
printed heading · Topic match: Reliability and curtailment
The IRAS Filing proposes to establish new criteria for the participation of New Large Loads, 2 associated new capacity that enters to serve New Large Loads called BYONC or 1 Proposal of PJM Interconnection, L.L.C.Read this passage Filed comments: Reliability and curtailment
II. QUALIFICATIONS
printed heading
Prior to founding E-Cubed, I worked as a contractor and directly for PJM in Audubon, Pennsylvania from February 2008 until October 2016.Read this passage
III. THE CURRENT RPM CAPACITY MARKET TRADES A FUNGIBLE COMMODITY
printed heading
THE CURRENT RPM CAPACITY MARKET TRADES A FUNGIBLE COMMODITY IN THE SAME WAY OTHER COMMODITY MARKETS OPERATERead this passage
A. Commodity Markets Trade Fungible Commodities
printed heading
A commodity is fungible when it can be replaced with an identical commodity, regardless of source of the original or replacement commodity.13 13 See https://www.merriam-webster.com/dictionary/fungible. 7 17.Read this passage
B. UCAP as a Fungible Commodity
printed heading
The RAA defines Accredited UCAP as “the quantity of Unforced Capacity, as denominated in Effective UCAP, that an ELCC Resource is capable of providing in a given Delivery Year.”14 20.Read this passage
IV. UNDULY DISCRIMINATORY AND PREFERENTIAL ASPECTS OF IRAS.
printed heading
Further, PJM is proposing to create multiple types of loads (Large Loads 50 MW or greater)23 based on in-service time (New Large Loads on or after June 1, 2027)24 whereby an LSEs must procure a specific type of UCAP depending on the size of the load and the load’s online date.25 These loads will…Read this passage
A. Inclusion or Exclusion of Loads from the VRR Curve in the RPM BRAs or IAs
printed heading · Topic match: Reliability and curtailment
PJM proposes to exclude all New Large Loads that are not contracted with BYONC resources, defined by PJM as “Eligible New Large Loads,”27 from the VRR Curve that represents the demand for UCAP in the BRAs and IAs.28 Yet other loads, including other incremental loads, will be included in the VRR…Read this passage Filed comments: Reliability and curtailment
B. The Offer Requirements into RPM Auctions that Differ Between BYONC, RBP,
printed heading
PJM proposes that BYONC Resources contracted with New Large Load have must offer requirements into the RPM BRA and IA as price takers (offers equal to $0/MW-day UCAP) as such New Large Load will also be included in the VRR Curve.32 This raises issues regarding the treatment of BYONC versus Planned…Read this passage
C. Differential Capacity Accreditation Between BYONC Resources and All Other
printed heading · Topic match: Reliability and curtailment
BYONC resources are treated very differently, even though they change the configuration of the PJM generation fleet which impacts ELCC values.41 PJM’s proposed tariff language states, “For any generation or storage resource, the Accredited UCAP of any BYONC shall be the Accredited UCAP for the RPM…Read this passage Filed comments: Reliability and curtailment
D. The Implicit Restrictions on the LSEs and Loads with Whom Existing Capacity
printed heading
For New Large Loads to avoid IRAS, they must contract with BYONC.Read this passage
E. Disparate Treatment of Different Loads by Size and In-Service Date for
printed heading
Disparate Treatment of Different Loads by Size and In-Service Date for Compensation for Load Reductions in Real-Time Operations 49.Read this passage
F. Eligible New Large Load Providing IRAS is Compensated and Treated Differently
printed heading
Eligible New Large Load Providing IRAS is Compensated and Treated Differently from Load Reductions Taken by Economic Load Response, Pre-Emergency Load Response, and Emergency Load Response 51.Read this passage
Attachment K-Appendix.
printed heading
Attachment K-Appendix. 48 PJM OA, Schedule 1, Section 1.10(d). 20 resources, including LR, that exists except in the most extreme of circumstances.49 Additionally, PJM does not propose reductions from IRAS to be considered in LMP price formation nor compensating IRAS reductions at LMP. 53.Read this passage
V. IRAS CREATES MULTIPLE UCAP COMMODITIES OUT OF A ONCE FUNGIBLE
printed heading
IRAS CREATES MULTIPLE UCAP COMMODITIES OUT OF A ONCE FUNGIBLE COMMODITY 56.Read this passage
A. UCAP from Existing Capacity Resources
printed heading
UCAP from Existing Capacity Resources can only be used to serve existing loads or new loads that do not qualify as New large Load.Read this passage
B. UCAP from BYONC Resources
printed heading
BYONC Resources are of a different vintage than all other UCAP resource types.Read this passage
VI. IMPLIED PROPERTY RIGHTS CREATED AND GRANTED BY IRAS
printed heading
IMPLIED PROPERTY RIGHTS CREATED AND GRANTED BY IRAS 62.Read this passage
A. Property Rights of Existing Capacity Resources Have Been Reallocated to Existing
printed heading
Property Rights of Existing Capacity Resources Have Been Reallocated to Existing Load by Fiat 65.Read this passage
B. Property Rights to Energy In Real-time Operations has Been Assigned to Eligible New
printed heading
Property Rights to Energy In Real-time Operations has Been Assigned to Eligible New Large Load in IRAS without any Upfront Purchase of Energy 68.Read this passage
VII. MARKET
printed heading
MARKET INEFFICIENCIES, MISPLACED INCENTIVES, AND POOR RELIABILITY OUTCOMES THAT WILL RESULT FROM IRAS 73.Read this passage
A. The Incentives Under IRAS Likely Will Not Bring the New Entry that PJM Expects
printed heading
The Incentives Under IRAS Likely Will Not Bring the New Entry that PJM Expects 75.Read this passage
B. Existing Capacity Resources Will Have Incentives to Exit the Market if New Entry
printed heading
Existing Capacity Resources Will Have Incentives to Exit the Market if New Entry Does Occur. 80.Read this passage
C. New Large Loads Will Have Incentives to Inefficiently Reduce Their Size to Avoid
printed heading · Topic match: Registry access
While PJM proposes to aggregate affiliated new loads within one mile of each other, there is no reason a load cannot be more widely dispersed to avoid application of IRAS. 84.Read this passage Filed comments: Registry access
VIII. CONCLUSIONS AND A WAY FORWARD BY LEARNING THE LESSONS OF
printed heading · Topic match: Reliability and curtailment
In fact, what PJM proposes in curtailing certain customers under IRAS goes back to the natural gas industry practices prior to the NGPA in curtailing certain customers.60 90.Read this passage Filed comments: Reliability and curtailment