ER26-3515-000 · 2026-09-03 · PJM Industrial Customer Coalition

Comments of the PJM Industrial Customer Coalition in response to the Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy Service…

Text extracted from the eLibrary original (SHA-256 3ba7c5f8041b27cd…). Download the original from the official source.

Contents · 9 sections
  1. I. BACKGROUND p. 1
  2. II. INTRODUCTION & EXECUTIVE SUMMARY p. 3
  3. III. COMMENTS p. 5
  4. A. Existing Large Loads Should Be Excluded from the Large Load Registry. p. 5
  5. B. Ordinary Load Fluctuations Should Not Subject Existing Retail Customers to p. 8
  6. C. Incremental Expansions Should Trigger IRAS Obligations Only for the Net p. 10
  7. D. IRAS Participants Should Not Receive Compensation That Shifts Costs to p. 12
  8. E. PJM’s Definition of New Large Load Should Track with PJM’s BTMG Rules. p. 14
  9. IV. CONCLUSION p. 15

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

In PJMICC’s view, the rules to accommodate new large load growth must be fair to existing customers but also crafted to support the economic growth of the region.
Read this passage Filed comments: Registry access

I. BACKGROUND

printed heading · Topic match: Reliability and curtailment

ER26-3515-000 (Aug. 13, 2026) (“IRAS Filing”). 2 PJM’s IRAS Filing proposes revisions to the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) and the PJM Open Access Transmission Tariff (“Tariff”) to establish the Interim Resource Adequacy Service (“IRAS”).
Read this passage Filed comments: Reliability and curtailment

II. INTRODUCTION & EXECUTIVE SUMMARY

printed heading · Topic match: Reliability and curtailment

If existing loads are included for informational purposes, they must be clearly exempted from all IRAS operational obligations — including curtailment, BYONC requirements, and RPM auction adjustments — and any collected data must be subject to robust confidentiality protections.  Second, ordinary…
Read this passage Filed comments: Reliability and curtailment

III. COMMENTS

printed heading

III.
Read this passage

A. Existing Large Loads Should Be Excluded from the Large Load Registry.

printed heading · Topic match: Registry access

The Large Load Registry proposes collecting substantial operational data, raising new privacy concerns for existing customers who should not be subject to the IRAS.
Read this passage Filed comments: Registry access

B. Ordinary Load Fluctuations Should Not Subject Existing Retail Customers to

printed heading · Topic match: Reliability and curtailment

As PJM states in the IRAS Filing, IRAS is designed as a “supplemental capacity product through which New Large Loads provide a load reduction service.”10 PJM drafted the IRAS Filing, including the proposed definition of New Large Load, to address resource adequacy challenges on the grid primarily…
Read this passage Filed comments: Reliability and curtailment

C. Incremental Expansions Should Trigger IRAS Obligations Only for the Net

printed heading

First, as a threshold matter, PJM must be clear that only incremental expansion should be classified as New Large Load.
Read this passage

D. IRAS Participants Should Not Receive Compensation That Shifts Costs to

printed heading · Topic match: Cost allocation

As a legal matter, States may not undermine FERC-jurisdictional rates.17 However, States are also limited, as a practical matter of rate setting, in allocating rates in a manner inconsistent with the underlying 16 The White House, Ratepayer Protection Pledge (Mar. 4, 2026), available at…
Read this passage Filed comments: Cost allocation

E. PJM’s Definition of New Large Load Should Track with PJM’s BTMG Rules.

printed heading · Topic match: Connecting load and generation

In the IRAS Filing, PJM mentions co-located load, but it does not explain how Behind- the-Meter Generation (“BTMG”) rules interact with IRAS obligations.18 In PJM’s Co-Located Load proceeding before the FERC, the Commission has ordered PJM to maintain Behind-the- Meter Generation (“BTMG”) rules for…
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading · Topic match: Cost allocation

These measures would go a long way to ensuring the IRAS program is just and reasonable and that existing retail customers are protected, consistent with the Ratepayer Protection Pledge.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

Dated this 3rd day of September, 2026. /s/ Susan E.