Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 08/13/2026 filing to establish Interim Resource Adequacy Service et al
Text extracted from the eLibrary original (SHA-256 b7406e043a5b4d5a…). Download the original from the official source.
Contents · 7 sections
- I. INTRODUCTION
- II. COMMENTS
- A. Peak Shaving Adjustment Should Be Credited in the Eligible New Large
- B. Opportunities for DR/DER Aggregation as BYONC Should be Clarified and
- C. IRAS Includes Important Elements That Should Be Maintained
- III. RETAIL COST ALLOCATION AND STATE COORDINATION
- IV. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
United recognizes and agrees with the rationale behind IRAS: New large loads that are contributing to the region’s resource adequacy shortfall, i.e., those that do not bring their own new capacity, should be the first to face curtailment if and when load shed is needed.Read this passage Filed comments: Reliability and curtailment
I. INTRODUCTION
printed heading · Topic match: Reliability and curtailment
United does not oppose the concept of a curtailment and BYONC mechanism as a necessary tool to manage an urgent reliability challenge, but United’s support for the specific approach taken in IRAS is tempered by a fundamental issue: PJM’s proposal assumes a degree of control over retail-level…Read this passage Filed comments: Reliability and curtailment
II. COMMENTS
printed heading · Topic match: Reliability and curtailment
COMMENTS United respectfully identifies the following specific clarifications and commitments needed to ensure IRAS achieves its intended purpose without creating unnecessary barriers to the very loads and resources best positioned to help close PJM’s resource adequacy gap.Read this passage Filed comments: Reliability and curtailment
A. Peak Shaving Adjustment Should Be Credited in the Eligible New Large
printed heading · Topic match: Reliability and curtailment
This is the same gap United’s RBP comments identify with respect to the RBP peak- shaving opt-out, and United’s RBP comments recommend the Commission direct PJM to amend the Eligible New Large Load Amount formula in this proceeding.6 This docket is where that recommendation must be resolved.Read this passage Filed comments: Reliability and curtailment
B. Opportunities for DR/DER Aggregation as BYONC Should be Clarified and
printed heading · Topic match: Reliability and curtailment
In summary, United requests that PJM create a clear mechanism for reactivated DR/DER sites to be considered “new” for BYONC, comparable to reactivated generation, without categorically excluding aggregations that participated before the 2026/2027 Delivery Year. ii.Read this passage Filed comments: Reliability and curtailment
C. IRAS Includes Important Elements That Should Be Maintained
printed heading · Topic match: Registry access
IRAS Includes Important Elements That Should Be Maintained United supports several elements of IRAS that will promote fair outcomes and recognize the standing value of demand-side and alternative capacity solutions and urges that these elements be maintained in IRAS or any successor curtailment and…Read this passage Filed comments: Registry access
III. RETAIL COST ALLOCATION AND STATE COORDINATION
printed heading · Topic match: Reliability and curtailment
ER26-3380-000, at 7-11 (filed Aug. 21, 2026). 18 Proposed Tariff, Attachment DD-4, §§ VI(b)(ii)(1)-(2); Transmittal Letter at 54-55. 19 Transmittal Letter at 37. 10 region’s resource adequacy shortfall, should be the first to face curtailment if and when load shed is needed.Read this passage Filed comments: Reliability and curtailment
IV. CONCLUSION
printed heading · Topic match: Reliability and curtailment
CONCLUSION United recognizes the unfortunate reality that curtailment of new large loads may be necessary to ensure reliability for existing customers in PJM as demand rises faster than supply and conceptually supports introduction of a mechanism to ensure that curtailment impacts those customers…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated this 3rd day of September, 2026. /s/ Mike HaughRead this passage