Protest of the Independent Market Monitor for PJM to the 08/13/2026 filing by PJM Interconnection, L.L.C. proposing to establish Interim Resource Adequacy…
Text extracted from the eLibrary original (SHA-256 aad0e9543eb2a2a6…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3515
Topics in the text: Reliability and curtailment · Cost allocation · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
Pursuant to that authority, we find that PJM’s Tariff appears to be unjust and unreasonable or unduly discriminatory or preferential because it lacks sufficiently clear and consistent provisions regarding the study process related to the provision of transmission service to Eligible Customers on…Read this passage Filed comments: Cost allocation
I. PROTEST
printed heading
I.Read this passage
A. The IRAS Filing Has Not Been Shown to be Just and Reasonable.
printed heading · Topic match: Reliability and curtailment
The rules for resource adequacy in a multistate region are necessarily beyond the jurisdiction of any PJM state and must be addressed at the federal level.Read this passage Filed comments: Reliability and curtailment
B. The IRAS Filing Is Deficient, Unjust and Unreasonable.
printed heading · Topic match: Reliability and curtailment
Although the IRAS Filing never states this explicitly, the IRAS Filing requires that data centers that do not bring new capacity must pay for capacity through the PJM capacity market cost allocation mechanism.Read this passage Filed comments: Reliability and curtailment
C. Rejecting the IRAS Filing Would Allow the Commission to Direct an
printed heading · Topic match: Reliability and curtailment
LSEs would require data centers without new capacity to provide curtailment service through a contract with a curtailment coordinator for up to three years or other reasonable defined limit.58 PJM would determine penalties for noncompliance with curtailment directives and other requirements as…Read this passage Filed comments: Reliability and curtailment
II. CONCLUSION
printed heading
CONCLUSION The Market Monitor respectfully requests that the Commission afford due consideration to this pleading as the Commission resolves the issues raised in this proceeding.Read this passage
ATTACHMENT A
printed heading · Topic match: Reliability and curtailment
LSEs would be obligated, as a condition of service, in the RAA, to require that all data centers that an LSE serves must have a bilateral contract with a new source of generation that meets the requirements to be exempt from curtailment, or to either establish themselves as curtailment coordinators…Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated at Eagleville, Pennsylvania, this 3rd day of September, 2026.Read this passage