Limited Protest of American Municipal Power, Inc. to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing
Text extracted from the eLibrary original (SHA-256 cf7017db03f9e8b0…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Cost allocation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
American Municipal Power, Inc. (“AMP”) hereby protests the August 17, 2026 compliance filing by PJM Interconnection, L.L.C. (“PJM”) in the above-captioned docket,1 in which PJM proposes revisions to its Open Access Transmission Tariff (“Tariff”) to comply with directives in the Federal Energy…Read this passage
I. BACKGROUND AND INTRODUCTION
printed heading · Topic match: Connecting load and generation
P 222. 10 PJM proposed defining Retail Behind The Meter Generation as: “Behind The Meter Generation that is used to serve a retail load served by a Network Customer located at the same electrical location (not including back-up generation at the same electrical location as the retail load that can…Read this passage Filed comments: Connecting load and generation
II. PROTEST
printed heading
II.Read this passage
A. The Commission should direct PJM to revise the proposed definition
printed heading · Topic match: Cost allocation
The PJM Filing proposes to define Eligible Load as “Co-Located Load or load connected to Behind the Meter Generation.”19 This definition appears to comply with the Commission’s directives in the June 18 Order inasmuch as it would encompass all “load 16 See PJM Filing, Transmittal Letter at 13…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully requests that the Commission direct PJM to revise its proposed definition of Eligible Generating Facility as described herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 8th day of September, 2026. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.comRead this passage