Joint Comments and Limited Protest of PJM Industrial Customer Coalition et al. to PJM Interconnection, L.L.C.'s 08/17/2026 Compliance Filing
Text extracted from the eLibrary original (SHA-256 55b796953a1d1edf…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ) Docket No.Read this passage Filed comments: Filing procedure
I. SUMMARY
printed heading · Topic match: Connecting load and generation
On March 11, 2026, Amtrak intervened in the above-captioned docket. 2 Behind-the-Meter Generation (“BTMG”) will remain designated as having BTMG as opposed to being classified as Co-Located Load more generally.Read this passage Filed comments: Connecting load and generation
II. BACKGROUND
printed heading · Topic match: Connecting load and generation
The Commission ordered PJM to submit a new compliance filing within 60 4 On December 18, 2025, the Commission issued the December Order, finding that the PJM Tariff is unjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and…Read this passage Filed comments: Connecting load and generation
III. THE INDUSTRIALS & AMTRAK
printed heading · Topic match: Filing procedure
Amtrak consumes substantial 6 On January 20, 2026, PJMICC and IECA jointly filed a Request For Clarification or, in the Alternative, Rehearing of the Industrial Customer Coalitions (“December Order Rehearing Request”), in Docket No.Read this passage Filed comments: Filing procedure
IV. COMMENTS & LIMITED PROTEST
printed heading · Topic match: Connecting load and generation
Any Interconnection Customer with an effective Interconnection Service Agreement that plans to use a Customer Facility to serve Co-Located Load must provide Transmission Provider and Interconnected Transmission Owner with advance written notice to begin the Necessary Studies process provided in…Read this passage Filed comments: Connecting load and generation
V. CONCLUSION & REQUEST FOR RELIEF
printed heading
CONCLUSION & REQUEST FOR RELIEF The Industrials and Amtrak respectfully request that the Commission direct PJM to modify its August Compliance Filing, consistent with the Industrials and Amtrak’s Joint Comments and Limited Protest.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 8th day of September, 2026. /s/ Matthew L.Read this passage