ER26-3515-000 · 2026-09-18 · Buckeye Power, Inc.

Motion for Leave to Answer and Answer of Buckeye Power, Inc. to certain Comments and Protests re PJM Interconnection, LLC’s proposal to Establish Interim…

Text extracted from the eLibrary original (SHA-256 b63bccb09d0ccbe0…). Download the original from the official source.

Contents · 7 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 2
  2. II. ANSWER p. 3
  3. A. Buckeye is a Self-Supply LSE. p. 4
  4. B. Buckeye supports limiting the definition of New Large Load to p. 6
  5. C. In the alternative, Buckeye supports removing existing loads p. 8
  6. D. At a minimum, the Commission should adopt PJM ICC’s p. 9
  7. III. CONCLUSION p. 9

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

Buckeye seeks to provide additional information and context that will assist the Commission in its decision-making process, particularly as it relates to the impact of PJM Interconnection, L.L.C.’s (“PJM”) Interim Resource Adequacy Service (“IRAS”) proposal on self-supply entities like Buckeye.
Read this passage Filed comments: Registry access

I. MOTION FOR LEAVE TO ANSWER

printed heading

MOTION FOR LEAVE TO ANSWER Buckeye respectfully requests leave to answer the comments and protests filed in the above-captioned proceeding on September 3, 2026.
Read this passage

II. ANSWER

printed heading · Topic match: Reliability and curtailment

It is not just and reasonable to impose IRAS requirements on existing loads experiencing organic load growth when a Self-Supply LSE has planned for and obtained generation to cover that same load growth To avoid this unjust and unreasonable outcome, Buckeye requests the Commission clarify or direct…
Read this passage Filed comments: Reliability and curtailment

A. Buckeye is a Self-Supply LSE.

printed heading · Topic match: Reliability and curtailment

Despite Buckeye having excess generation in its portfolio built and paid for by its members for the very purpose of supplying this growth, Buckeye or the load must now go out and build or acquire an additional 6 MW of new generation to serve this growth or be subject to curtailment under PJM’s IRAS…
Read this passage Filed comments: Reliability and curtailment

B. Buckeye supports limiting the definition of New Large Load to

printed heading · Topic match: Reliability and curtailment

Cir. 1982). 23 PJM Filing, Transmittal Letter at 122. - 8 - the scope of New Large Loads to data centers would be consistent with the purpose of IRAS because the data center loads that are driving the resource adequacy concerns would still be subject to BYONC or curtailment.
Read this passage Filed comments: Reliability and curtailment

C. In the alternative, Buckeye supports removing existing loads

printed heading · Topic match: Reliability and curtailment

Similar to the discussion above, this modification of PJM’s proposal would be consistent with IRAS’s overall objectives, since it would still require data centers that are causing the resource adequacy problems identified by PJM to be subject to either BYONC or curtailment. - 9 -
Read this passage Filed comments: Reliability and curtailment

D. At a minimum, the Commission should adopt PJM ICC’s

printed heading · Topic match: Reliability and curtailment

As proposed by PJM ICC: “When an existing Large Load facility expands, only load growth over 50 MW from the baseline should be subject to IRAS. (That is, a 50 MW facility should not be subjected to IRAS until it expands beyond 100 MW.)”24 This clarification would avoid the absurd result described…
Read this passage Filed comments: Reliability and curtailment

III. CONCLUSION

printed heading

CONCLUSION To the extent PJM does not address the issues described above on its own, Buckeye requests the Commission direct PJM to (i) revise the definition of New Large Loads to apply only to data centers, or, in the alternative; (ii) limit the definition of New Large Loads only to loads that are…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated on this 18th day of September, 2026. /s/ Jeffrey M.