Motion for Leave to Answer and Answer of American Electric Power Service Corporation to PJM Interconnection, L.L.C.'s 09/10/2026 Answer
Text extracted from the eLibrary original (SHA-256 fdc0420a1ce5d22e…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Most of these flaws emanate from the proposal that a departing member not just cover its load obligations for RBP Charges, but also hold third-party generators harmless through some combination of accelerated payments, pseudo-ties, or renegotiated contracts, depending on which generators PJM elects…Read this passage
I. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER While an answer to a protest or comment is generally not permitted under the Commission’s rules,3 AEP respectfully moves for leave to file this Answer and asks that the Commission consider this response.4 The Commission permits an answer when it provides useful and…Read this passage
II. ANSWER
printed heading
II.Read this passage
A. AEP’s Protest Provided Detailed Concerns Regarding the Proposed RBP
printed heading · Topic match: Cost allocation
PJM’s proposed exit provisions would create, for the first time, a long-term financial obligation that a departing Transmission Owner must satisfy as a condition of withdrawal—an obligation that could extend up to 15 years and could amount to billions of dollars.Read this passage Filed comments: Cost allocation
B. PJM’s Answer Does Not Provide a Basis for the Commission to Approve
printed heading · Topic match: Cost allocation
It is inadequate to simply state, as PJM does, that “it must retain” that discretion to ensure reliability and resource adequacy.12 Without governing principles, the RBP exit provisions would ultimately afford PJM considerable discretion over a Transmission Owner’s ability to withdraw.Read this passage Filed comments: Cost allocation
C. The RBP Exit Provisions Represent a Fundamental Change to the
printed heading
The RBP Exit Provisions Represent a Fundamental Change to the Framework for Withdrawal from PJM that PJM Has Not Justified The proposed provisions would materially alter the financial calculus of RTO withdrawal in a manner that is untested and unprecedented.Read this passage
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, AEP respectfully requests that the Commission grant this motion for leave to answer, accept this Answer, and grant the relief requested herein.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that, on this 18th day of September, 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the captioned proceedings. /s/ Emily Beard Emily Beard TROUTMAN PEPPER LOCKE LLP 401 9th Street,…Read this passage