ER26-3515-000 · 2026-10-07 · Southern Maryland Electric Cooperative, Inc.

Motion for Leave to File Limited Answer and Answer of Southern Maryland Electric Cooperative, Inc. to PJM Interconnection, L.L.C.'s 09/23/2026 Answer

Text extracted from the eLibrary original (SHA-256 de6c56e30de5e2a6…). Download the original from the official source.

Contents · 8 sections
  1. I. Introduction and Summary p. 1
  2. II. Motion for Leave to Answer p. 2
  3. III. Answer p. 3
  4. A. PJM Did Not Respond to SMECO's Showing That an IRAS Action Could Require p. 3
  5. B. PJM Did Not Respond to SMECO's Protest of the Billing Indemnification Provision. p. 5
  6. C. PJM Did Not Address SMECO's Large Load Registry Concerns, and Its Statements to p. 6
  7. D. The Commission Can Resolve These Issues Through Prescriptive Compliance Directives. p. 7
  8. IV. Conclusion p. 8

Read topic-matched comments in ER26-3515

Topics in the text: Registry access · Reliability and curtailment · Credit and exit

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C. ) Docket No.
Read this passage

I. Introduction and Summary

printed heading · Topic match: Reliability and curtailment

As the filing utility under section 205 of the Federal Power Act ("FPA"), PJM bears the burden of demonstrating that its proposal is just and reasonable.6 The New Jersey Board of Public Utilities ("NJBPU"), moreover, has filed an answer supporting SMECO's position on the first of these issues.7…
Read this passage Filed comments: Reliability and curtailment

II. Motion for Leave to Answer

printed heading

SMECO respectfully requests that the Commission accept this Answer.
Read this passage

III. Answer

printed heading

III.
Read this passage

A. PJM Did Not Respond to SMECO's Showing That an IRAS Action Could Require

printed heading · Topic match: Reliability and curtailment

PJM Did Not Respond to SMECO's Showing That an IRAS Action Could Require Curtailment of Core Native Load.
Read this passage Filed comments: Reliability and curtailment

B. PJM Did Not Respond to SMECO's Protest of the Billing Indemnification Provision.

printed heading · Topic match: Credit and exit

In its Limited Protest, SMECO showed that proposed Tariff, Attachment DD-4, section X(b)(iii) provides that any default in the payment of IRAS compensation "shall be assessed to the Electric Distributor," not to PJM or its membership. 22 In restructured states, the defaulting LSE may have no…
Read this passage

C. PJM Did Not Address SMECO's Large Load Registry Concerns, and Its Statements to

printed heading · Topic match: Registry access

It does not, however, resolve SMECO's concern, for three reasons: • Proposed Tariff, Attachment DD-4, section III(b) still provides that an Electric Distributor "shall" provide Registry information and coordinate with PJM on its validity.
Read this passage Filed comments: Registry access

D. The Commission Can Resolve These Issues Through Prescriptive Compliance Directives.

printed heading

PJM asks that, to the extent the Commission rejects any element of its filing, the Commission "either direct prescriptive changes to be implemented on compliance or provide guidance" to PJM and stakeholders.34 SMECO's requests are limited and can be addressed in that manner. 30 PJM Answer at 9–10,…
Read this passage

IV. Conclusion

printed heading

Conclusion For the foregoing reasons, SMECO respectfully requests that the Commission (1) grant SMECO leave to file this Limited Answer and accept it into the record; and (2) in acting on the IRAS Filing, direct PJM to make the clarifications and revisions described above and in SMECO’s initial…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated: October 7, 2026. /s/ _____ John S.
Read this passage