ER26-3515-000 · 2026-10-08 · Monitoring Analytics, LLC

Answer and Motion for Leave to Answer of the Independent Market Monitor for PJM to the 09/23/2026 Answer of PJM Interconnection, L.L.C

Text extracted from the eLibrary original (SHA-256 7bff4d30ee476f5c…). Download the original from the official source.

Contents · 6 sections
  1. I. ANSWER p. 4
  2. A. Neither the IRAS Filing nor the Market Monitor’s Proposed Remedial p. 4
  3. B. PJM Can File a Complete Proposal Consistent with the Pledge and Principles p. 6
  4. C. The IRAS Filing Has Not Been Shown to be Just and Reasonable. p. 10
  5. II. MOTION FOR LEAVE TO ANSWER p. 24
  6. III. CONCLUSION p. 24

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

The IRAS Filing is PJM’s non responsive response to broad agreement among policy makers, regulators, and developers, captured in the Ratepayer Protection Pledge and Principles, on the need to ensure that data centers bring their own new generation and pay their own way and to prioritize the…
Read this passage Filed comments: Cost allocation

I. ANSWER

printed heading

I.
Read this passage

A. Neither the IRAS Filing nor the Market Monitor’s Proposed Remedial

printed heading · Topic match: Cost allocation

ER26-3380-000 (September 10, 2026) at 64 (“It is fallacious to suggest that a just and reasonable cost allocation approach must either identify specific loads (which are - 5 - additional rules to address the central issue, to assign RBP auctions costs (at PP 150–157), finding “PJM has not…
Read this passage Filed comments: Cost allocation

B. PJM Can File a Complete Proposal Consistent with the Pledge and Principles

printed heading · Topic match: Reliability and curtailment

That is of no legal consequence.”). 13 See RBP Filing at 64 (“It is fallacious to suggest that a just and reasonable cost allocation approach must … identify specific loads (which are not FPA-jurisdictional actors) …”). 14 See RAA Schedules 9, et seq. & 10 (rules for PJM to evaluate capability and…
Read this passage Filed comments: Reliability and curtailment

C. The IRAS Filing Has Not Been Shown to be Just and Reasonable.

printed heading · Topic match: Reliability and curtailment

PJM proposes to set a final and unchangeable ELCC value, and therefore a fixed UCAP MW, for each BYONC arrangement at the level for which the BYONC first cleared.26 27 The ELCC rating used to establish the initial UCAP value will be in place for up to 15 years.
Read this passage Filed comments: Reliability and curtailment

II. MOTION FOR LEAVE TO ANSWER

printed heading · Topic match: Filing procedure

MOTION FOR LEAVE TO ANSWER The Commission’s Rules of Practice and Procedure, 18 CFR § 385.213(a)(2), do not permit answers to protests, answers, or requests for rehearing unless otherwise ordered by the decisional authority.
Read this passage Filed comments: Filing procedure

III. CONCLUSION

printed heading

CONCLUSION The Market Monitor respectfully requests that the Commission afford due consideration to this answer as the Commission resolves the issues raised in this proceeding.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Eagleville, Pennsylvania, this 8th day of October, 2026.