ER26-3531-000 · 2026-10-09 · Midcontinent Independent System Operator Inc.

Motion for Leave to Answer and Answer of Midcontinent Independent System Operator Inc. to the Motion for Leave to Answer and Answer filed by American…

Text extracted from the eLibrary original (SHA-256 028d6af855e5b390…). Download the original from the official source.

Contents · 8 sections
  1. I. INTRODUCTION p. 2
  2. II. MOTION FOR LEAVE TO FILE ANSWER p. 2
  3. III. ANSWER p. 3
  4. A. ATC’s Proposed Tariff Changes Do Not Address the Concerns Raised in p. 3
  5. B. ATC’S Proposals Exceed the Limits of Local Planning Criteria and Would p. 5
  6. IV. COMMUNICATIONS p. 8
  7. V. NOTICE AND SERVICE p. 8
  8. VI. CONCLUSION p. 8

Read topic-matched comments in ER26-3531

Topics in the text: Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Accordingly, MISO reiterates the concerns noted in its limited protest and its requests that the Commission direct ATC to revise Attachment FF-ATCLLC either to: (1) align with MISO’s pending Interconnection Reliability Requirements Proposal (“IRR”) and other large load filings related to FERC’s…
Read this passage Filed comments: Filing procedure

I. INTRODUCTION

printed heading

Correspondingly, MISO requests that the Commission should (1) allow ATC’s requirements only where MISO has no corresponding requirement, as proposed in the transitional framework discussed below; or (2) in cases where MISO has an established framework, allow ATC to impose stricter requirements…
Read this passage

II. MOTION FOR LEAVE TO FILE ANSWER

printed heading

MOTION FOR LEAVE TO FILE ANSWER MISO requests permission to submit this Answer to provide additional information related to the issues raised in ATC’s answer and assist the Commission in its decision-making.
Read this passage

III. ANSWER

printed heading

III.
Read this passage

A. ATC’s Proposed Tariff Changes Do Not Address the Concerns Raised in

printed heading

ATC’s Proposed Tariff Changes Do Not Address the Concerns Raised in MISO’s Answer and Will Create Further Misalignments In its Answer, ATC proposes to modify its Large Load definition as follows; • ATC’s large load criteria will apply within the ATC footprint.
Read this passage

B. ATC’S Proposals Exceed the Limits of Local Planning Criteria and Would

printed heading · Topic match: Cost allocation

Any burdens that exist must be weighed against the benefits of such regional uniformity—specifically including fairness, transparency, consistency, the avoidance of cost shifts, maintaining regional reliability, and promoting commercial certainty in the Midwest region.
Read this passage Filed comments: Cost allocation

IV. COMMUNICATIONS

printed heading

COMMUNICATIONS MISO requests waiver of Rule 203(b)(3)10 of the Commission’s Rules of Practice and Procedure to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all communications related to this filing be directed…
Read this passage

V. NOTICE AND SERVICE

printed heading

NOTICE AND SERVICE MISO has served a copy of this filing electronically, including attachments, upon each person designated on the official service list compiled by the Secretary as well as on all Tariff customers, MISO Members, Member representatives of transmission owners and non- transmission…
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION WHEREFORE, MISO respectfully requests that the Commission (i) accept this Answer; and (ii) direct ATC to revise Attachment FF-ATCLLC as requested in MISO’s Limited Protest; and (iii) to the extent that the Commission determines that a transition would alleviate process 10 18 C.F.R. §…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 9th day of October 2026, in Carmel, Indiana. /s/ Julie Bunn Julie Bunn Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, IN 46032 317-249-5400