EL25-49-000 · 2026-10-22 · Vistra Corp.

Petition for Review filed in the U.S. Court of Appeals for the Third Circuit of Vistra Corp. re 12/18/2025, 02/20/2026, 06/18/2026, and 08/20/2026 Orders,

Text extracted from the eLibrary original (SHA-256 76c09b385d836083…). Download the original from the official source.

Contents · 63 sections
  1. ATTACHMENT A p. 8
  2. I. Background p. 12
  3. A. Show Cause Order p. 12
  4. B. Behind the Meter Generation p. 15
  5. C. Eligible Customer p. 16
  6. II. PJM’s Answer to Show Cause Order and Responsive Pleadings29 p. 18
  7. A. PJM’s Options for Co-Location Arrangements p. 18
  8. B. General p. 21
  9. C. Jurisdiction p. 23
  10. D. Cost Allocation p. 31
  11. E. Interconnection Procedures and Cost Allocation p. 51
  12. Attachment M-3 was designed for supplemental transmission projects, not load p. 60
  13. F. PJM Capacity Market, Reliability, and Resource Adequacy p. 64
  14. G. Other Arguments p. 72
  15. III. Notice of Show Cause Proceeding and Responsive Pleadings p. 75
  16. IV. Discussion p. 77
  17. A. Procedural Matters p. 77
  18. B. Substantive Matters p. 77
  19. Conclusion p. 148
  20. ATTACHMENT B p. 151
  21. ATTACHMENT C p. 155
  22. A. Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand p. 162
  23. B. Additional Charge for Eligible Customers Taking FCD and/or NFCD p. 162
  24. C. Interconnection Requirements and Operational Practices for Necessary Control p. 163
  25. D. Penalty Charge or Other Remedial Action for New Transmission Services.- 218 - p. 163
  26. G. Curtailment Procedures for Interim NITS and Non-Firm Contract Demand p. 163
  27. I. Background p. 164
  28. A. February Order p. 164
  29. B. December Order p. 166
  30. II. Notice of Filings and Responsive Pleadings p. 169
  31. A. PJM’s Compliance Filing p. 169
  32. B. Paper Hearing on New Transmission Services p. 170
  33. III. Procedural Matters p. 171
  34. IV. Requests for Rehearing and/or Clarification p. 173
  35. A. Jurisdiction p. 174
  36. B. Show Cause Findings p. 181
  37. C. Replacement Rate p. 207
  38. D. Informational Report p. 252
  39. V. Compliance p. 254
  40. A. BTMG Rules p. 254
  41. B. Transmission Service p. 282
  42. C. Necessary Studies p. 290
  43. D. Other p. 298
  44. E. Effective Date p. 309
  45. VI. Paper Hearing p. 310
  46. A. Rates, Terms, and Conditions for Firm and Non-Firm Contract p. 311
  47. B. Additional Charge for Eligible Customers Taking FCD and/or NFCD p. 354
  48. C. Interconnection Requirements and Operational Practices for p. 363
  49. D. Penalty Charge or Other Remedial Action for New Transmission p. 373
  50. E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission p. 392
  51. F. Communications, Alarm, SCADA, or Other Requirements p. 395
  52. G. Curtailment Procedures for Interim NITS and Non-Firm Contract p. 396
  53. H. Rates, Terms, and Conditions for Interim NITS p. 401
  54. Attachment F-3A. Last, Indicated TOs request that PJM add a placeholder section for p. 403
  55. I. Annual Report on New Transmission Services p. 411
  56. ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0) p. 429
  57. ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0) p. 429
  58. ATTACHMENT D p. 435
  59. ATTACHMENT E p. 440
  60. F. Alvin Taylor p. 459
  61. F. Alvin Taylor p. 472
  62. F. Alvin Taylor p. 480
  63. F. Alvin Taylor p. 496

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Vistra petitions for review of the aforementioned Commission orders on the grounds that they are arbitrary and capricious, reflect a failure to engage in reasoned decision-making, are not supported by substantial evidence, and are otherwise contrary to law.1 This petition for review is timely filed…
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

Instructions Pursuant to Rule 26.1, Federal Rules of Appellate Procedure any nongovernmental corporate party to a proceeding before this Court must file a statement identifying all of its parent corporations and listing any publicly held company that owns 10% or more of the party’s stock.
Read this passage

ATTACHMENT A

printed heading · Topic match: Connecting load and generation

As discussed below, we find that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission…
Read this passage Filed comments: Connecting load and generation

I. Background

printed heading

I.
Read this passage

A. Show Cause Order

printed heading · Topic match: Connecting load and generation

EL25-49-000, et al. - 7 - Commission stated that, while both Co-Located Load and non-co-located load may have similar resource adequacy impacts, the speed at which Co-Located Load can be added to the grid may pose particular resource adequacy challenges, especially if Co-Location Arrangements are…
Read this passage Filed comments: Connecting load and generation

B. Behind the Meter Generation

printed heading

Transmission rates for NITS and Point-to-Point Service (PTPS) are based on transmission formula rates filed by the transmission owners.
Read this passage

C. Eligible Customer

printed heading · Topic match: Cost allocation

This definition forms the basis for PJM’s existing transmission cost allocation approach, through which each Eligible Customer is billed for the charges associated with the transmission services used to serve its load. 28 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions – E-F (41.0.0) (defining…
Read this passage Filed comments: Cost allocation

II. PJM’s Answer to Show Cause Order and Responsive Pleadings29

printed heading

PJM’s Answer to Show Cause Order and Responsive Pleadings29
Read this passage

A. PJM’s Options for Co-Location Arrangements

printed heading · Topic match: Connecting load and generation

PJM requests that, if “the record supports consideration of additional options,” the Commission issue detailed guiding principles that PJM can operationalize in an FPA section 205 filing.31 13.
Read this passage Filed comments: Connecting load and generation

B. General

printed heading · Topic match: Connecting load and generation

According to Indicated Transmission Owners, all load in PJM must be designated as Network Load and served by a Network Customer (or take PTPS), thereby ensuring this load pays its fair share of transmission costs.
Read this passage Filed comments: Connecting load and generation

C. Jurisdiction

printed heading · Topic match: Connecting load and generation

Several parties support the Commission’s exercise of jurisdiction over the taking of transmission service.67 Market Monitor and UCS argue that Co-Location Arrangements are interconnected to the transmission grid and receive jurisdictional service from jurisdictional transmission facilities.68 CATF…
Read this passage Filed comments: Connecting load and generation

D. Cost Allocation

printed heading · Topic match: Connecting load and generation

Indicated Transmission Owners suggest that adding a definition of Co-Located Load to the PJM Tariff specifying that co-located must be either Network Load or served by PTPS and does not meet the definition of BTMG may clarify expectations and obligations associated with such load.114 Indicated…
Read this passage Filed comments: Connecting load and generation

E. Interconnection Procedures and Cost Allocation

printed heading · Topic match: Connecting load and generation

Bloom proposes an alternative to PJM’s option 6 to adopt reforms to interconnect generation and Co-Located Load (both new) as a composite facility called an “energy park,” instead of studying the load in one process and the generation in another.224 106.
Read this passage Filed comments: Connecting load and generation

Attachment M-3 was designed for supplemental transmission projects, not load

printed heading · Topic match: Cost allocation

Attachment M-3 was designed for supplemental transmission projects, not load interconnection, and is not suitable for large load interconnection.249 EDFR asks the Commission to provide guidance to PJM and other Regional Transmission Organization or Independent System Operator (RTO/ISO) and…
Read this passage Filed comments: Cost allocation

F. PJM Capacity Market, Reliability, and Resource Adequacy

printed heading · Topic match: Connecting load and generation

Market Monitor argues that there should be no artificial incentives or changes to fundamental capacity market rules that allow preferential treatment of large loads.274 OPSI states that Capacity Resources cannot prioritize serving non-PJM load, even as backup, without undermining system reliability…
Read this passage Filed comments: Connecting load and generation

G. Other Arguments

printed heading · Topic match: Cost allocation

A number of parties urge that any Commission action in this proceeding provide flexibility for different regions325 and/or different co-location configurations.326 California Utilities request that the Commission recognize that approaches to co-located facilities must be tailored to account for…
Read this passage Filed comments: Cost allocation

III. Notice of Show Cause Proceeding and Responsive Pleadings

printed heading · Topic match: Connecting load and generation

On September 19, 2025, a letter from then-Chairman Rosner to PJM was filed in this proceeding; then-Chairman Rosner’s letter requests information on load forecasting.
Read this passage Filed comments: Connecting load and generation

IV. Discussion

printed heading

IV.
Read this passage

A. Procedural Matters

printed heading

Pursuant to Rule 214(d) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.214(d), we grant the late-filed motions to intervene given these entities’ interests in the proceeding, the early stage of the proceeding, and the absence of undue prejudice or delay. 158.
Read this passage

B. Substantive Matters

printed heading · Topic match: Connecting load and generation

As the Commission explained in Order No. 845, Interconnection Customers may seek provisional interconnection service when available studies or additional studies as necessary indicate that there is a level of interconnection service that can occur without any additional Interconnection Facilities…
Read this passage Filed comments: Connecting load and generation

Conclusion

printed heading · Topic match: Cost allocation

As we establish new transmission services, it cannot come at the expense of other ratepayers.
Read this passage Filed comments: Cost allocation

ATTACHMENT B

printed heading · Topic match: Filing procedure

As provided in 16 U.S.C. § 825l(a), the requests for rehearing of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such section.
Read this passage Filed comments: Filing procedure

ATTACHMENT C

printed heading · Topic match: Filing procedure

The Commission directed PJM to file, within 60 days of the date of issuance of the order, a compliance filing to revise its Tariff to set forth specific terms and conditions that an Interconnection Customer in PJM seeking to serve Co-Located Load must follow to effectuate a Co-Location Arrangement.
Read this passage Filed comments: Filing procedure

A. Rates, Terms, and Conditions for Firm and Non-Firm Contract Demand

printed heading

A.
Read this passage

B. Additional Charge for Eligible Customers Taking FCD and/or NFCD

printed heading

B.
Read this passage

C. Interconnection Requirements and Operational Practices for Necessary Control

printed heading

C.
Read this passage

D. Penalty Charge or Other Remedial Action for New Transmission Services.- 218 -

printed heading

Penalty Charge or Other Remedial Action for New Transmission Services.- 218 - 1.
Read this passage

G. Curtailment Procedures for Interim NITS and Non-Firm Contract Demand

printed heading · Topic match: Reliability and curtailment

G.
Read this passage Filed comments: Reliability and curtailment

I. Background

printed heading

I.
Read this passage

A. February Order

printed heading · Topic match: Connecting load and generation

As to specific concerns raised regarding Co-Location Arrangements, the Commission found that the Tariff may be unjust, unreasonable, unduly discriminatory, or preferential because it does not specify the transmission service that Co-Location Arrangements must take, if any, or otherwise provide a…
Read this passage Filed comments: Connecting load and generation

B. December Order

printed heading · Topic match: Connecting load and generation

Specifically, the Commission found the Tariff unjust and unreasonable because there is a lack of sufficient clarity or consistency as to the rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load.25 As part of the replacement rate, the Commission…
Read this passage Filed comments: Connecting load and generation

II. Notice of Filings and Responsive Pleadings

printed heading

II.
Read this passage

A. PJM’s Compliance Filing

printed heading · Topic match: Registry access

ER26-1479-000 was published in the Federal Register, 91 Fed.
Read this passage Filed comments: Registry access

B. Paper Hearing on New Transmission Services

printed heading · Topic match: Registry access

EL25-49-002, et al. - 16 - Consumer Advocate filed a motion to intervene out of time in this proceeding.
Read this passage Filed comments: Registry access

III. Procedural Matters

printed heading · Topic match: Filing procedure

Pursuant to section 313(a) of the FPA,44 an aggrieved party must file an application for rehearing within 30 days after the issuance of the Commission’s order; in this case, that deadline is 40 Pennsylvania Office of Consumer Advocate is not a party to this proceeding with respect to rehearing or…
Read this passage Filed comments: Filing procedure

IV. Requests for Rehearing and/or Clarification

printed heading · Topic match: Connecting load and generation

We also set aside, in part, the December Order; we find that requiring Eligible Customers taking transmission service on behalf of load with BTMG to take NITS, without the option to instead take such alternative transmission services, would be unjust and unreasonable for the same reasons we made…
Read this passage Filed comments: Connecting load and generation

A. Jurisdiction

printed heading · Topic match: Filing procedure

We nonetheless reiterate that: (1) Eligible Customers taking transmission service on behalf of Co-Located Load must have the option to take one of three transmission services, i.e., NITS or Interim NITS, FCD transmission service, or NFCD transmission service;66 and (2) while it remains just and…
Read this passage Filed comments: Filing procedure

B. Show Cause Findings

printed heading · Topic match: Connecting load and generation

In fact, based on our review of the Tariff, the Tariff indeed does not contain provisions specifying the rules governing Co-Location Arrangements.115 For instance, the Tariff lacks provisions specifying: the terms and conditions for Interconnection Customers seeking to use their generators to serve…
Read this passage Filed comments: Connecting load and generation

C. Replacement Rate

printed heading · Topic match: Filing procedure

In the December Order, the Commission found that the Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load and Eligible…
Read this passage Filed comments: Filing procedure

D. Informational Report

printed heading

EL26-67-000, we direct PJM to show cause as to why its Tariff remains just and reasonable without sufficiently clear and consistent Tariff provisions that address the application process for requesting transmission service to Eligible Customers on behalf of large loads and the study procedures for…
Read this passage

V. Compliance

printed heading

V.
Read this passage

A. BTMG Rules

printed heading · Topic match: Reliability and curtailment

As such, we find that PJM’s proposed 50 MW materiality threshold is more likely to help maintain resource adequacy and reliability relative to a larger threshold.521 Whereas Constellation argues that PJM’s proposed materiality threshold of 50 MW is too high and unsupported, we agree with PJM that…
Read this passage Filed comments: Reliability and curtailment

B. Transmission Service

printed heading · Topic match: Connecting load and generation

The December Order stated that Interim NITS must allow an Eligible Customer that has requested NITS on behalf of a Co-Located Load to take non-firm transmission service that can be interrupted until the Network Upgrades necessary to provide NITS are complete and the Co-Located Load can be…
Read this passage Filed comments: Connecting load and generation

C. Necessary Studies

printed heading · Topic match: Connecting load and generation

The Commission directed PJM to revise the Tariff to clarify that an existing Interconnection Customer seeking to modify its ISA or GIA to allow its generator to serve Co-Located Load, including to reflect any reduction in its CIRs, must follow the Necessary Study process to effectuate such…
Read this passage Filed comments: Connecting load and generation

D. Other

printed heading · Topic match: Connecting load and generation

However, we reject PJM’s proposed revisions to comply with the Commission’s directive in the December Order to require Interconnection Customers with ISAs or GIAs executed (or requested to be filed unexecuted) prior to the effective date of the revised generation interconnection procedures and pro…
Read this passage Filed comments: Connecting load and generation

E. Effective Date

printed heading · Topic match: Reliability and curtailment

PJM requests a placeholder effective date of 12/31/9998 because PJM cannot implement the Tariff changes until the Commission sets the terms and conditions of the new transmission services in the paper hearing.731 PJM states that it will submit a clean-up filing proposing an effective date after the…
Read this passage Filed comments: Reliability and curtailment

VI. Paper Hearing

printed heading · Topic match: Connecting load and generation

The Commission directed PJM to modify its Tariff to require that the Eligible Customer taking transmission service on behalf of a Co-Located Load takes one of three transmission services: (1) NITS or Interim NITS, (2) FCD transmission service, or (3) NFCD transmission service.735 With respect to…
Read this passage Filed comments: Connecting load and generation

A. Rates, Terms, and Conditions for Firm and Non-Firm Contract

printed heading · Topic match: Connecting load and generation

We therefore direct PJM to submit a compliance filing within 60 days of the issuance of this order proposing Tariff revisions to permit Eligible Customers to elect to take FCD transmission service or NFCD transmission service without the limitations that PJM proposes (i.e., (1) the requirement that…
Read this passage Filed comments: Connecting load and generation

B. Additional Charge for Eligible Customers Taking FCD and/or NFCD

printed heading · Topic match: Cost allocation

Constellation contends that Indicated TOs’ proposed Grid Reliance Charge rests on an unsound methodology that violates cost causation principles.934 Constellation requests that the charge be recalculated based on the “minimum system” method.
Read this passage Filed comments: Cost allocation

C. Interconnection Requirements and Operational Practices for

printed heading · Topic match: Connecting load and generation

More specifically, Constellation supports, subject to clarification, Indicated TOs’ recommendations that: (1) all special protection schemes and remedial action schemes be fully redundant; (2) customers should pay for PJM and transmission owner-administered studies to ensure any special protection…
Read this passage Filed comments: Connecting load and generation

D. Penalty Charge or Other Remedial Action for New Transmission

printed heading · Topic match: Reliability and curtailment

However, we reject PJM’s proposal not to apply such a penalty to Eligible Customers taking FCD transmission service on behalf of Co-Located Load, consistent with our findings above that Eligible Customers taking FCD transmission service on behalf of Co-Located Load must also have necessary control…
Read this passage Filed comments: Reliability and curtailment

E. Anti-Toggling Mechanisms for Firm Contract Demand Transmission

printed heading · Topic match: Connecting load and generation

PJM proposes an anti-toggling mechanism to prevent transmission customers from switching between FCD and NFCD transmission services by providing that the portion of the Co-Located Load served by FCD transmission service is not eligible to be served by NFCD transmission service for five years…
Read this passage Filed comments: Connecting load and generation

F. Communications, Alarm, SCADA, or Other Requirements

printed heading · Topic match: Connecting load and generation

PJM proposes to develop telemetry requirements for Co-Located Load so that PJM can monitor the status of demand placed on PJM’s transmission system, including unreserved use, to ensure reliability.1068 PJM states that it still determining the scope of the tools and requirements necessary to limit…
Read this passage Filed comments: Connecting load and generation

G. Curtailment Procedures for Interim NITS and Non-Firm Contract

printed heading · Topic match: Reliability and curtailment

Joint Co-Location Developers argue that PJM fails to adequately clarify when and how NFCD transmission service and Interim NITS shall be curtailed, in particular the curtailment trigger.1074 Joint Co-Location Developers maintain that the curtailment trigger significantly affects rates and service…
Read this passage Filed comments: Reliability and curtailment

H. Rates, Terms, and Conditions for Interim NITS

printed heading · Topic match: Connecting load and generation

PJM proposes load shedding and curtailment provisions applicable to Interim NITS, including that prior to commencement of service, the Eligible Customer must demonstrate its ability to comply with PJM’s load shedding and curtailment procedures.1094 PJM proposes to require Eligible Customers taking…
Read this passage Filed comments: Connecting load and generation

Attachment F-3A. Last, Indicated TOs request that PJM add a placeholder section for

printed heading · Topic match: Connecting load and generation

Enchanted Rock reiterates that PJM’s implementation of Interim NITS is fundamentally flawed because, while an Eligible Customer takes Interim NITS on behalf of a Co-Located Load, PJM proposes not to allow that Co-Located Load to receive any capacity or energy from a Co-Located Generator and instead…
Read this passage Filed comments: Connecting load and generation

I. Annual Report on New Transmission Services

printed heading · Topic match: Connecting load and generation

Maryland OPC requests that the Commission at minimum require PJM demonstrate how its proposal meets ratepayer protection standards set forth in the Statement of Principles and Ratepayer Protection Pledge and defer action on the proposed revisions until after PJM proposes tariff revisions to…
Read this passage Filed comments: Connecting load and generation

ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0)

printed heading

ATTACHMENT F-3A, OATT ATTACHMENT F-3A (0.0.0) •
Read this passage

ATTACHMENT F-4, OATT ATTACHMENT F-4 (0.0.0)

printed heading · Topic match: Cost allocation

In today’s order, the Commission addresses rehearing requests and the paper hearing and compliance record regarding the rates, terms, and conditions through which Co-Located Loads may take transmission service from the PJM Interconnection, L.L.C. (PJM) system.
Read this passage Filed comments: Cost allocation

ATTACHMENT D

printed heading · Topic match: Filing procedure

As provided in 16 U.S.C. § 825l(a), the requests for rehearing of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such section.
Read this passage Filed comments: Filing procedure

ATTACHMENT E

printed heading

ATTACHMENT E SERVICE LIST Case: 26-3635 Document: 1-1 Page: 439 Date Filed: 10/19/2026 Party Primary Person or Counsel of Record to be Served Other Contact to be Served Andrew Hinz Andrew Hinz 1427 PARK AVE BALTIMORE, MARYLAND 21217 UNITED STATES ahinz61@outlook.com Advanced Energy United Michael…
Read this passage

F. Alvin Taylor

printed heading

Alvin Taylor Attorney McCarter & English, LLP 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 UNITED STATES ataylor@mccarter.com Case: 26-3635 Document: 1-1 Page: 458 Date Filed: 10/19/2026 EDF Renewables, Inc.
Read this passage

F. Alvin Taylor

printed heading

Alvin Taylor Attorney McCarter & English, LLP 1301 K Street, NW Suite 1000 West Washington, DISTRICT OF COLUMBIA 20005 ataylor@mccarter.com Lee County Electric Cooperative, Inc.
Read this passage

F. Alvin Taylor

printed heading · Topic match: Registry access

Dearborn Street Chicago, ILLINOIS 60603 UNITED STATES carlos.isaac@exeloncorp.com Stan Berman 3502 Fremont Ave N, #1 Seattle, WASHINGTON 98103 stan@bermlaw.com Pennsylvania Office of Consumer Advocate Melanie El Atieh Deputy Consumer Advocate Pennsylvania Office of Consumer Advocate 555 WALNUT ST…
Read this passage Filed comments: Registry access

F. Alvin Taylor

printed heading

P. 17 (a), the agency must file the record with this Court within forty (40) days after being served with the petition for review, unless the statute authorizing review provides otherwise.
Read this passage