ER27-532-000 · 2026-11-16 · California Independent System Operator Corporation

Att-C_Draft-Final-Proposal-Large-Load

Text extracted from the eLibrary original (SHA-256 7e4bf4d2acd236a8…). Download the original from the official source.

Contents · 15 sections
  1. Attachment C – Final Proposal p. 1
  2. C. Co-Location Arrangements and Load with Behind-the-Meter Generation49 p. 3
  3. D. Extending New Transmission Services to Eligible Customers Taking Service on p. 3
  4. E. Interconnection Customers Serving Electrically Proximate Large Load and Co- p. 3
  5. I. Executive Summary p. 4
  6. A. Developing procedures to improve coordination related to load interconnection p. 4
  7. B. Upholding a workable framework for the PTOs to develop just and reasonable p. 4
  8. C. Establishing parallel information and application requirements for co-located p. 4
  9. D. Creating a framework for new interconnection service to allow large loads to p. 4
  10. E. Considering the need for a process to study generating facilities serving p. 4
  11. A. Transmission Service to Eligible Customers on Behalf of p. 11
  12. B. Cost Shifting Among Transmission Customers p. 42
  13. C. Co-Location Arrangements and Load with Behind-the-Meter p. 50
  14. D. Extending New Transmission Services to Eligible Customers p. 64
  15. E. Interconnection Customers Serving Electrically Proximate p. 69

Read the parent filing

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Attachment C – Final Proposal

printed heading

Attachment C – Final Proposal Large Loads Tariff Amendment California Independent System Operator Corporation November 16, 2026 Large Load Enhancements Draft Final Proposal September 24, 2026 Prepared by: Sarah Goldmuntz Danielle Mills Bill Weaver California Independent System Operator Large Loads…
Read this passage

Table of Contents

printed heading · Topic match: Cost allocation

Transmission Service to Eligible Customers on Behalf of Large Loads . 10 1.
Read this passage

C. Co-Location Arrangements and Load with Behind-the-Meter Generation49

printed heading · Topic match: Cost allocation

Co-Location Arrangements and Load with Behind-the-Meter Generation49 1.
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on

printed heading

D.
Read this passage

E. Interconnection Customers Serving Electrically Proximate Large Load and Co-

printed heading

E.
Read this passage

I. Executive Summary

printed heading · Topic match: Cost allocation

This coordination includes anticipating demand growth, exploring the complexities of co-located and flexible loads, ensuring equitable cost allocation, and considering new technical requirements to account for changing operational profiles.
Read this passage

A. Developing procedures to improve coordination related to load interconnection

printed heading

Developing procedures to improve coordination related to load interconnection applications, studies, technical standards, and operational requirements for accurate long-term planning and near-term reliability.
Read this passage

B. Upholding a workable framework for the PTOs to develop just and reasonable

printed heading · Topic match: Cost allocation

Upholding a workable framework for the PTOs to develop just and reasonable deposit, financing, and other cost allocation structures within their tariffs.
Read this passage

C. Establishing parallel information and application requirements for co-located

printed heading

Establishing parallel information and application requirements for co-located arrangements in the CAISO’s generator interconnection process to align with PTO load interconnection studies.
Read this passage

D. Creating a framework for new interconnection service to allow large loads to

printed heading · Topic match: Connecting load and generation

Creating a framework for new interconnection service to allow large loads to interconnect quickly to the transmission system while waiting for network upgrade completion.
Read this passage

E. Considering the need for a process to study generating facilities serving

printed heading · Topic match: Reliability and curtailment

To give the PTOs direction for their filings, the CAISO proposes consistent minimum standards throughout this draft final proposal.
Read this passage

A. Transmission Service to Eligible Customers on Behalf of

printed heading · Topic match: Connecting load and generation

The CAISO therefore proposes a framework for agreements under which large loads commit to limiting energy withdrawals under the flexible load interconnection service offerings described in Section D of this draft final proposal.
Read this passage

B. Cost Shifting Among Transmission Customers

printed heading · Topic match: Cost allocation

To manage concerns around cost shifting caused by one PTO having a greater number of large load interconnections than other PTOs, the CAISO proposes the following: All PTOs should take into account the impact of construction contributions, revenues, or other cost offsets37 associated with network…
Read this passage

C. Co-Location Arrangements and Load with Behind-the-Meter

printed heading · Topic match: Connecting load and generation

Serving Co-Located Loads The Commission stated in the Order that the CAISO’s tariff does not contain provisions addressing with sufficient clarity and consistency the rates, terms, and conditions of service that apply to interconnection customers serving co-located load.48 The Commission included,…
Read this passage

D. Extending New Transmission Services to Eligible Customers

printed heading · Topic match: Connecting load and generation

Viridon suggested that curtailment obligations must be enforceable and the chain of authority clear: the CAISO directs, the UDC/LSE implements the curtailment with the end-use customer, and the interconnecting PTO acts only pursuant to CAISO or Reliability Coordinator operating instructions.
Read this passage

E. Interconnection Customers Serving Electrically Proximate

printed heading · Topic match: Connecting load and generation

Proposal The CAISO proposes considering provisions for interconnection customers to serve electrically proximate large loads in a future stakeholder initiative.
Read this passage