ER27-532-000 · 2026-11-16 · California Independent System Operator Corporation

2026-11-16 Large Load Tariff Amendment: Resubmission under different filing code

CAISO files its large load tariff amendment a second time on November 16, 2026, in ER27-532-000, under a different filing code. The text is identical to its filing in ER27-506-000: a 50 MW large load definition, co-location disclosure by generators, and a Flexible Interim Load Interconnection service. Deposits, security and cost recovery sit in the owners' tariffs.

Asks FERC to: Accept the revisions effective February 16, 2027, with scheduling coordinator changes on November 1, 2027 and settlement changes on April 30, 2028.

Filed under section 205 to answer the E-10 show cause order for CAISO. This is a resubmission of the ER27-506 filing under a different filing code, with the same page text.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5) E-10 CAISO: Application / study process (P 5, p. 25) E-10 CAISO: Cost-recovery agreement (§ III.B.3, p. 25) E-10 CAISO: Service for flexible loads (§ III.D, p. 62) E-10 CAISO: BTMG netting (pp. 60-61, p. 60)

Key points

  1. CAISO says its revisions, with the transmission owners', answer the show cause order.
    Taken together, the CAISO and Participating Transmission Owner (PTO) tariff revisions supply the tariff-level clarity, customer protections, and operational tools the Order seeks. PDF p. 1
  2. Deposits, security and cost recovery are left to each transmission owner's tariff.
    the PTOs will implement just and reasonable deposit, security, reimbursement, and cost-recovery provisions in their own tariffs PDF p. 3
  3. Generator interconnection customers must disclose plans to serve co-located load.
    requires generator interconnection customers to disclose plans to serve co- located load PDF p. 3
  4. The interim service lets flexible loads energize before network upgrades are finished.
    The CAISO’s Flexible Interim Load Interconnection (FILI) can permit earlier energization while network upgrades are pending PDF p. 3
  5. A permanent flexible service is left for later work.
    with additional work planned on permanent flexibility and other emerging configurations PDF p. 3
  6. A large load is a single site of 50 MW or more.
    and that has a peak load of 50 MW or greater. PDF p. 11
  7. Loads already operating or with a complete request before February 16, 2027 are not treated as large loads.
    the CAISO will not consider any load a large load subject to the CAISO tariff where the load is operational or has a complete request with the PTO before the CAISO tariff revisions’ effective date of February 16, 2027 PDF p. 13
  8. CAISO asks for a February 16, 2027 effective date.
    the CAISO requests that the Commission accept the tariff revisions contained in this filing effective February 16, 2027 PDF p. 46

Text extracted from the eLibrary original (SHA-256 ca3237a5dfe7cff2…). Download the original from the official source.

Contents · 23 sections
  1. I. Executive Summary p. 1
  2. II. Background p. 4
  3. A. Large Loads p. 4
  4. B. Key CAISO Differences p. 6
  5. III. Tariff Revisions and Order to Show Cause p. 11
  6. A. Transmission Service to Eligible Customers on Behalf of Large p. 11
  7. B. Cost Shifting Risk among Transmission Customers p. 24
  8. C. Co-Location Arrangements and Load with Behind the Meter p. 27
  9. D. Extending New Transmission Services to Eligible Customers p. 35
  10. E. Interconnection Customers Serving Electrically Proximate p. 38
  11. F. Future Issues p. 40
  12. IV. Briefing Questions p. 42
  13. V. Order to Show Cause p. 45
  14. VI. Effective Date, Comment Period, Request for Waiver p. 46
  15. VII. Communications p. 47
  16. VIII. Service p. 47
  17. IX. Contents of Filing p. 47
  18. Attachment A p. 47
  19. Attachment B p. 47
  20. Attachment C p. 47
  21. Attachment D p. 47
  22. Attachment E p. 47
  23. X. Conclusion p. 48

Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

www.caiso.com │ 250 Outcropping Way, Folsom, CA 95630 │ 916.351.4400 California Independent System Operator Corporation November 16, 2026 The Honorable Debbie-Anne A.
Read this passage

I. Executive Summary

printed heading · Topic match: Connecting load and generation

The Commission’s Order asks whether the CAISO tariff remains just and reasonable as unprecedented large load growth tests utility tariffs nationwide.
Read this passage

II. Background

printed heading

II.
Read this passage

A. Large Loads

printed heading · Topic match: Cost allocation

The CAISO’s Issue Paper, posted in January 2026, described current roles, considerations, and processes for large loads, including transmission and resource planning, transmission service offerings, cost allocation and responsibility, technical requirements and standards, operational requirements,…
Read this passage

B. Key CAISO Differences

printed heading · Topic match: Cost allocation

Large loads must still complete applicable interconnection studies, satisfy technical and operating requirements, and fund or await required facilities and network upgrades.
Read this passage

III. Tariff Revisions and Order to Show Cause

printed heading

Tariff Revisions and Order to Show Cause Although the CAISO believes the tariff revisions in this filing do not substantially affect Order Nos. 888, 1000, 2003, 792, 845, 2023, or 1920 policies, the CAISO’s proposed tariff revisions meet both the just and reasonable standard and the independent…
Read this passage

A. Transmission Service to Eligible Customers on Behalf of Large

printed heading · Topic match: Reliability and curtailment

Prior to the interconnection of any large load to the CAISO controlled grid, the CAISO proposes to require the PTO to provide the CAISO with the following information for the large load: Load type, variable or flat load designation, expected hourly operating profile, points of interconnection and…
Read this passage

B. Cost Shifting Risk among Transmission Customers

printed heading · Topic match: Cost allocation

The CAISO believes that the PTOs may develop their own proposals to address any cost shifting, and that the current transmission revenue requirement and credit mechanisms in the transmission access charges can accommodate those proposals.78 The CAISO proposes some metering and settlement changes in…
Read this passage

C. Co-Location Arrangements and Load with Behind the Meter

printed heading · Topic match: Connecting load and generation

Co-located Interconnection Studies The Commission stated in the Order that the CAISO’s tariff does not contain provisions addressing with sufficient clarity and consistency the rates, terms, and conditions of service that apply to interconnection customers serving co-located load.86 The Commission…
Read this passage

D. Extending New Transmission Services to Eligible Customers

printed heading · Topic match: Connecting load and generation

Reese November 16, 2026 Page 36 in the PJM Co-Location Order.”122 The Commission then explained that the customer “must have necessary control technologies and/or protection systems, which may include a special protection scheme, to limit its energy withdrawals to its approved level,” which are…
Read this passage

E. Interconnection Customers Serving Electrically Proximate

printed heading · Topic match: Connecting load and generation

Interconnection Customers Serving Electrically Proximate Large Load and Co-Located Load The Commission preliminarily found in the Order that the CAISO tariff appears to be unjust and unreasonable because it does not contain provisions allowing an interconnection customer to seek the generator…
Read this passage

F. Future Issues

printed heading · Topic match: Reliability and curtailment

All parties must work to ensure compliance maintains reliability without being unduly burdensome.
Read this passage

IV. Briefing Questions

printed heading · Topic match: Reliability and curtailment

We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with network upgrades triggered by large loads.” Order to Show Cause at P 125.
Read this passage

V. Order to Show Cause

printed heading

Order to Show Cause The Commission should conclude the Order to Show Cause proceeding.
Read this passage

VI. Effective Date, Comment Period, Request for Waiver

printed heading

Effective Date, Comment Period, Request for Waiver With the exception of the two sections described below, the CAISO requests that the Commission accept the tariff revisions contained in this filing effective February 16, 2027 (i.e., 92 days after the date of this filing).142 Although the CAISO is…
Read this passage

VII. Communications

printed heading

Communications Pursuant to Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure,144 the CAISO requests that all correspondence, pleadings, and other communications regarding this filing should be directed to the following: William H.
Read this passage

VIII. Service

printed heading

Service The CAISO has served copies of this filing on the CPUC, the CEC, and all parties with scheduling coordinator agreements under the CAISO tariff.
Read this passage

IX. Contents of Filing

printed heading

Contents of Filing In addition to this transmittal letter, this filing includes the following attachments:
Read this passage

Attachment A

printed heading

Attachment A Clean CAISO tariff sheets incorporating this tariff amendment
Read this passage

Attachment B

printed heading

Attachment B Red-lined document showing the revisions in this tariff amendment
Read this passage

Attachment C

printed heading

Attachment C Final Proposal
Read this passage

Attachment D

printed heading

Attachment D Technical Working Group Proposal
Read this passage

Attachment E

printed heading

Attachment E Board Memorandum 144 18 C.F.R. § 385.203(b)(3).
Read this passage

X. Conclusion

printed heading

Conclusion For the reasons set forth above, the CAISO respectfully requests that the Commission accept the CAISO’s proposed tariff revisions and conclude the Order to Show Cause proceeding.
Read this passage