ER27-513-000 · 2026-11-16 · Pacific Gas and Electric Company

Response to 11/16/2026, Show Cause Order of Pacific Gas and Electric Company

Pacific Gas and Electric files a two-page notice in the show cause docket, EL26-71-000, on November 16, 2026. It says its section 205 filing was assigned ER27-513-000. The notice has no proposals of its own; the substance is in the earlier filing.

Records that PG&E used the section 205 route the E-10 show cause order allowed, and points the EL26-71 record to the new docket where the proposal sits.

E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. PG&E reports its section 205 filing and the docket it received.
    submitted a Section 205 filing responsive to the Order to Show Cause in Docket No. EL26-71-000, which was assigned a new docket number ER27-513-000 PDF p. 1
  2. The notice gives the earlier filing's eLibrary accession number.
    which was assigned a new docket number ER27-513-000, with eLibrary accession number 20261116-5257 PDF p. 1

Text extracted from the eLibrary original (SHA-256 ed3f2babe6590ce7…). Download the original from the official source.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Pacific Gas and Electric Company Docket No.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Oakland, California, this 16th day of November, 2026. /s/ Gurjap Singh __ Gurjap Singh Pacific Gas and Electric Company FERC Electric Proceedings Dept. 300 Lakeside Drive Oakland, California 94612-3534 E-mail: Gurjap.Singh@pge.com
Read this passage