large_load_customer_concept_report_-_jan_2026
Text extracted from the eLibrary original (SHA-256 eaaf6e028c90add4…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 1.
Opening text
opening text
2Read this passage
INTRODUCTION
printed heading · Topic match: Connecting load and generation
While perspectives differed, several themes emerged: ● Location and timing of capacity matter more than systemwide averages. ● Utilities are actively searching for bridge strategies that offer near-term capacity relief while long-term upgrades are built. ● Verification and accreditation must be…Read this passage Filed comments: Connecting load and generation
BACKGROUND
printed heading · Topic match: Reliability and curtailment
Similarly, the Piclo "Clubbing" Model6 proposes that data centers should move beyond consideration of creating flexibility internally and instead procure resource adequacy from local VPPs.Read this passage Filed comments: Reliability and curtailment