Comments of the Alliance to Save Energy in support of clear, durable rules that enable responsible large-load integration while preserving reliability, cost…
Text extracted from the eLibrary original (SHA-256 ca0b63be68c426ab…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Reliability and curtailment · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
At the same time, the record is equally clear that the Commission must guard against hidden reliability risks, unjustified cost shifts, and one-sided frameworks that either overbuild the system or let favored customers evade meaningful obligations.Read this passage Filed comments: Cost allocation
I. Grid Reliability & Planning: Integrating Large Loads While Leveraging Energy
printed heading · Topic match: Reliability and curtailment
This would respond directly to the core reliability concern in the record—whether the system must be planned for a given load—by tying favorable treatment to demonstrable reductions in that planning obligation.Read this passage Filed comments: Reliability and curtailment
II. Cost Allocation & Transmission Service Design: Conditions for Favorable Treatment
printed heading · Topic match: Cost allocation
Cost Allocation & Transmission Service Design: Conditions for Favorable Treatment The record sharply divides between parties favoring full Network Load treatment and parties favoring actual-use or net-impact approaches.Read this passage Filed comments: Cost allocation
III. Flexible Load & Demand-Side Capacity: Option 7, Option 8, and the Need for Strong
printed heading · Topic match: Reliability and curtailment
The Alliance to Save Energy recognizes that measurement and verification must strike a balance between rigor and practicality.Read this passage Filed comments: Reliability and curtailment
Conclusion
printed heading · Topic match: Reliability and curtailment
The Alliance to Save Energy therefore urges the Commission to ensure that whatever interconnection or service framework PJM ultimately adopts, whether for co-located load, flexible service, or broader large-load treatment, it includes a clear pathway for facilities to earn favorable treatment…Read this passage Filed comments: Reliability and curtailment