Motion for Leave to Answer and Answer of Geronimo Power, LLC in response to the reply briefs filed by PJM Interconnection, L.L.C. et al
Text extracted from the eLibrary original (SHA-256 84319f705297bd56…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Geronimo Power therefore respectfully requests leave to file this answer to the extent the Commission deems such leave is necessary and requests that the Commission consider this answer in its deliberations in this proceeding. 3 PJM Interconnection, L.L.C., et al., Docket Nos.Read this passage
I. ANSWER
printed heading
ANSWER At the heart of the Commission’s Show Cause Order5 lies a recognition that the current paradigm for serving large loads in PJM is not sufficiently flexible to accommodate the growth of hyperscale data centers and other large load customers that are essential for the nation’s economic…Read this passage
A. The Commission Should Reject PJM’s And The PJM Transmission Owners’
printed heading · Topic match: Connecting load and generation
If the system conditions that impose reliability risks arise, PJM can refuse to accommodate requests for this non-firm service.Read this passage Filed comments: Connecting load and generation
B. The PJM Transmission Owners Have Not Demonstrated That Charging The
printed heading · Topic match: Reliability and curtailment
Moreover, while the PJM Transmission Owners claim that “it is far from certain what upgrades may be required for Non-Firm Contract Demand Service customers” and thus assert that they cannot yet determine the appropriate discount they should provide to Non-Firm Contract Demand transmission…Read this passage Filed comments: Reliability and curtailment
C. The PJM Transmission Owners Have Not Demonstrated That Their Proposed
printed heading · Topic match: Connecting load and generation
Additionally, PJM has proposed to assess co-located load charges for black start and regulation service on a gross basis.31 It is thus unclear why co-located load should 28 PJM TO Reply at 23. 29 Geronimo Response at 12-14. 30 PJM Interconnection, L.L.C. et al., Docket Nos.Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION Geronimo Power respectfully requests that the Commission issue an order consistent with its filings in these proceedings.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 21st day of May 2026. /s/ Stephen J.Read this passage