AD26-7-000 · 2026-07-15 · PJM Industrial Customer Coalition

Pre-filed Statement of Susan Bruce, Counsel for PJM Industrial Customer Coalition, for the PJM Governance and Stakeholder Reforms Technical Conference

Text extracted from the eLibrary original (SHA-256 2003ffef0884771f…). Download the original from the official source.

Contents · 5 sections
  1. I. Background p. 2
  2. II. Response to Commission Questions p. 6
  3. A. PJM Governance Mechanics – Board Authority, States’ Role, Filing Rights, p. 6
  4. B. PJM Stakeholder Process – Design, Transparency, and Decision-making p. 13
  5. III. Conclusion p. 18

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms : Docket No.
Read this passage Filed comments: Cost allocation

I. Background

printed heading · Topic match: Reliability and curtailment

This change would signal that PJM’s responsibilities must be understood through the practical effects of its wholesale actions on retail customers, particularly in a modern grid where demand response, distributed resources, and shared responsibility for resource adequacy have blurred traditional…
Read this passage Filed comments: Reliability and curtailment

II. Response to Commission Questions

printed heading

II.
Read this passage

A. PJM Governance Mechanics – Board Authority, States’ Role, Filing Rights,

printed heading · Topic match: Registry access

Otherwise, PJM must submit any PJM OA or eligible Tariff change under Section 206 of the Federal Power Act.
Read this passage Filed comments: Registry access

B. PJM Stakeholder Process – Design, Transparency, and Decision-making

printed heading · Topic match: Reliability and curtailment

Because customer purchases account for roughly half of all market activity in the PJM region, and customers have invested billions of dollars in the region, customers must continue to have a strong voice in voting outcomes.
Read this passage Filed comments: Reliability and curtailment

III. Conclusion

printed heading

While PJMICC does not seek fundamental restructuring, PJMICC believes that certain changes are necessary to ensure PJM's stakeholder process can keep pace with the region's 19 evolving operational and market needs—and that any such changes must preserve, rather than diminish, the voice and…
Read this passage