ER26-3380-000 · 2026-08-17 · Individual No AffiliationPERSISTENCE ANALYTICS GROUP LLC

PAG_Comments_ER26-3380-000_Pre-Procurement_Assumption_Verification

Text extracted from the eLibrary original (SHA-256 8b8a0054ed9c72e9…). Download the original from the official source.

Contents · 7 sections
  1. I. THE COMMISSION SHOULD TREAT ASSUMPTION REVALIDATION AS A THRESHOLD p. 1
  2. II. CURRENT SUPPLY-SIDE EVIDENCE SHOULD BE REVALIDATED BEFORE THE PROCUREMENT p. 1
  3. III. DEMAND-SIDE MATURITY AND DURABILITY SHOULD BE TESTED WITH THE SAME p. 2
  4. IV. THE COMMISSION SHOULD REQUIRE DEFINED REVALIDATION TRIGGERS BEFORE AND p. 3
  5. V. THE COMMISSION SHOULD REQUIRE A DECISION-GRADE EVIDENTIARY RECORD, NOT p. 3
  6. VI. REQUESTED COMMISSION ACTION p. 3
  7. VII. CONCLUSION p. 4

Read the parent filing

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. THE COMMISSION SHOULD TREAT ASSUMPTION REVALIDATION AS A THRESHOLD

printed heading · Topic match: Cost allocation

The relevant decision chain is: forecast demand + accredited supply -> modeled shortfall -> evidence status -> sensitivity testing -> revalidation -> procurement quantity -> contract obligation -> cost allocation -> actual load -> realized ratepayer outcome.
Read this passage Filed comments: Cost allocation

II. CURRENT SUPPLY-SIDE EVIDENCE SHOULD BE REVALIDATED BEFORE THE PROCUREMENT

printed heading

CURRENT SUPPLY-SIDE EVIDENCE SHOULD BE REVALIDATED BEFORE THE PROCUREMENT QUANTITY IS FIXED A recent external analysis published by SemiAnalysis challenges aspects of PJM's resource- adequacy modeling, including the treatment of winter thermal capability and post-Storm Elliott winterization.
Read this passage

III. DEMAND-SIDE MATURITY AND DURABILITY SHOULD BE TESTED WITH THE SAME

printed heading · Topic match: Reliability and curtailment

DEMAND-SIDE MATURITY AND DURABILITY SHOULD BE TESTED WITH THE SAME DISCIPLINE The RBP is also expressly tied to resource adequacy challenges associated with large-load growth.
Read this passage Filed comments: Reliability and curtailment

IV. THE COMMISSION SHOULD REQUIRE DEFINED REVALIDATION TRIGGERS BEFORE AND

printed heading · Topic match: Cost allocation

For each trigger, the record should identify the responsible decision owner, the evidence required, the effect on the procurement quantity or cost allocation, and the disposition of unresolved exceptions.
Read this passage Filed comments: Cost allocation

V. THE COMMISSION SHOULD REQUIRE A DECISION-GRADE EVIDENTIARY RECORD, NOT

printed heading · Topic match: Cost allocation

It simply makes the evidentiary status of decision-critical assumptions visible before they are converted into contractual obligations and ratepayer exposure.
Read this passage Filed comments: Cost allocation

VI. REQUESTED COMMISSION ACTION

printed heading · Topic match: Cost allocation

REQUESTED COMMISSION ACTION PAG respectfully requests that, in acting on PJM's filing, the Commission require or direct PJM to provide a pre-procurement revalidation record that: • identifies the material supply-side and demand-side assumptions producing the procurement quantity; • states the…
Read this passage Filed comments: Cost allocation

VII. CONCLUSION

printed heading

For the foregoing reasons, PAG respectfully requests that the Commission require a transparent pre-procurement assumption-verification and revalidation record as part of its disposition of PJM's Reliability Backstop Procurement proposal.