Motion to Intervene and Request for Clarification, or in the Alternative, Limited Protest of Tract Holding Company I, LLC re PJM Interconnection, L.L.C.’s…
Text extracted from the eLibrary original (SHA-256 268ea02e5deadf27…). Download the original from the official source.
Contents · 8 sections
Read topic-matched comments in ER26-3380
Topics in the text: Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Cir. 2017).5 1 18 C.F.R. §§ 385.211, 385.212, 385.214. 2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No.Read this passage Filed comments: Reliability and curtailment
I. MOTION TO INTERVENE
printed heading
Accordingly, Tract requests that the Commission grant this motion, consistent with the public interest.Read this passage
II. COMMUNICATIONS
printed heading
COMMUNICATIONS Please address all notices and communications regarding this proceeding to the following persons who are also designated for service in this proceeding.Read this passage
III. BACKGROUND
printed heading · Topic match: Reliability and curtailment
Inc., 175 FERC ¶ 61,172, at P 16 n.20 (2021). 6 18 C.F.R. § 385.214. 3 additional supply to meet the resource adequacy needs of the PJM Region.”7 Following the 2027/2028 base residual auction clearing 5.6% short of PJM’s target reserve margin, on January 16, 2026, the PJM Board initiated a Critical…Read this passage Filed comments: Reliability and curtailment
IV. REQUEST FOR CLARIFICATION
printed heading
IV.Read this passage
A. PJM Should Clarify the Scope of Agreements Load Can Provide As Evidence
printed heading · Topic match: Reliability and curtailment
Tract respectfully requests that PJM clarify that the undefined terms “electric service agreement and transmission service agreement” encompass executed agreements with load serving entities or transmission owners that evidence a binding commitment by new load to achieve commercial operation by or…Read this passage Filed comments: Reliability and curtailment
V. LIMITED PROTEST
printed heading
V.Read this passage
A. To The Extent Not Clarified As Argued Above, PJM’s RBP Filing Is Unduly
printed heading · Topic match: Connecting load and generation
To The Extent Not Clarified As Argued Above, PJM’s RBP Filing Is Unduly Discriminatory Because It Excludes Similarly Situated New Loads From Eligibility For Qualifying RBP Offset UCAP MW and Annual Demand Resources or DER Capacity Aggregation Resources.Read this passage Filed comments: Connecting load and generation
VI. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, Tract respectfully requests that PJM provide the clarification requested herein, or, in the alternative, that the Commission sever and reject the relevant portion of PJM’s RBP filing as unduly discriminatory and direct PJM to submit revised tariff language on…Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that on this 21st day of August, 2026, a copy of the foregoing document has been electronically served upon each person designated on the official service list in this proceeding. /s/ Kathy Lowrey_ Kathy Lowrey 600 Fifth St NW Washington, D.C. 20001…Read this passage