Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers to PJM Interconnection, L.L.C.'s 08/13/2026…
Text extracted from the eLibrary original (SHA-256 4246bbe71c9155c2…). Download the original from the official source.
Contents · 15 sections
- I. INTRODUCTION AND SUMMARY
- II. MOTION TO INTERVENE
- A. Timeliness
- B. Identity of Movants
- C. Movants' Interest
- III. THE FILING
- IV. PROTEST
- A. PJM has not filed a rate. It has filed a range and deferred its value to a proceeding that
- B. PJM concedes that its framework cannot function without state action, and supplies no
- C. Delaware refutes PJM's premise.
- D. Section X(b)(iii) shifts uncollected wholesale obligations onto Delmarva's captive
- E. The Large Load Registry cannot perform the function PJM assigns it.
- F. The VRR Curve exclusion raises capacity prices for every customer in the zone, and
- V. RELIEF REQUESTED
- VI. CONCLUSION
Read topic-matched comments in ER26-3515
Topics in the text: Cost allocation · Registry access · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
ER26-3515-000 MOTION TO INTERVENE AND PROTEST OF NICHOLAS MAX NEAL AND DAVID NEAL, DELAWARE STANDARD OFFER SERVICE RATEPAYERS Pursuant to Rules 211, 212, and 214 of the Commission's Rules of Practice and Procedure, 18 C.F.R. §§ 385.211, 385.212, 385.214, and the Commission's Combined Notice of…Read this passage Filed comments: Cost allocation
I. INTRODUCTION AND SUMMARY
printed heading · Topic match: Cost allocation
PJM asks the Commission to accept a wholesale rate that has no value and a cost allocation that has no allocator. 2.Read this passage Filed comments: Cost allocation
II. MOTION TO INTERVENE
printed heading
II.Read this passage
A. Timeliness
printed heading · Topic match: Filing procedure
On September 2, 2026, the Commission denied the Organization of PJM States, Inc.'s ("OPSI") motion for an extension of time and confirmed that "[t]he deadline to submit interventions, protests, and comments in the above- referenced proceeding remains 5pm ET September 3, 2026." Notice Denying…Read this passage Filed comments: Filing procedure
B. Identity of Movants
printed heading
The Customer is a retail electric customer of Delmarva Power & Light Company ("DPL") taking service in the State of Delaware, within the DPL transmission zone of the PJM Region, under DPL Service Classification MGS-S (Medium General Service — Secondary).Read this passage
C. Movants' Interest
printed heading
Rule 214(b)(2) requires a movant to show an "interest which may be directly affected by the outcome of the proceeding," or that participation "is in the public interest." 18 C.F.R. § 385.214(b)(2)(ii), (iii).Read this passage
III. THE FILING
printed heading · Topic match: Registry access
PJM must therefore defend this filing on its own terms, without borrowing support from a proceeding it has disclaimed.Read this passage Filed comments: Registry access
IV. PROTEST
printed heading
IV.Read this passage
A. PJM has not filed a rate. It has filed a range and deferred its value to a proceeding that
printed heading · Topic match: Retail and wholesale authority
PJM proposes a rate "equal to 50% of the Non-Performance Charge Rate." IRAS Filing, transmittal at 102.Read this passage Filed comments: Retail and wholesale authority
B. PJM concedes that its framework cannot function without state action, and supplies no
printed heading · Topic match: Retail and wholesale authority
Here PJM proposes none, while relying on the same assumption of state action. 29.Read this passage Filed comments: Retail and wholesale authority
C. Delaware refutes PJM's premise.
printed heading · Topic match: Cost allocation
On October 14, 2025, the Delaware Public Service Commission opened Docket No. 25-0826 to establish a large load tariff, to ensure that "large load facilities, like data centers, do not shift costs to other ratepayers." That is the proceeding in which Delaware would adopt the "state-approved load…Read this passage Filed comments: Cost allocation
D. Section X(b)(iii) shifts uncollected wholesale obligations onto Delmarva's captive
printed heading
Where PJM bills at the Electric Distributor's request, "such billing will be viewed as a bilateral transaction between the Electric Distributor and the other party and any default shall be assessed to the Electric Distributor." Id. at 109; proposed Tariff, Attachment DD-4, § X(b)(iii). 37.Read this passage
E. The Large Load Registry cannot perform the function PJM assigns it.
printed heading · Topic match: Registry access
On the Registry itself, the ICC warned that "[s]tates have different rules that can limit their access to confidential data," that the ICC "would not be in a position to sign the pro forma non-disclosure agreements to access confidential data from PJM as it reads at this time," and that it "is…Read this passage Filed comments: Registry access
F. The VRR Curve exclusion raises capacity prices for every customer in the zone, and
printed heading · Topic match: Cost allocation
PJM's justification is the Ratepayer Protection Pledge — a voluntary commitment that appears in no tariff, binds no signatory, and cannot be enforced by this Commission or by any party.Read this passage Filed comments: Cost allocation
V. RELIEF REQUESTED
printed heading · Topic match: Cost allocation
Third, PJM must make the Large Load Registry information necessary to identify New Large Loads within a zone — at minimum identity, location, in-service date, and cumulative peak load quantity — available to the RERRA and the Electric Distributor for that zone on terms each is legally able to…Read this passage Filed comments: Cost allocation
VI. CONCLUSION
printed heading
PJM asks the Commission to approve a rate no one can compute and an allocation no one is required to make, and to make both effective on October 12, 2026.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Wilmington, Delaware, this 2nd day of September, 2026. /s/ David Neal _______________________________ David NealRead this passage