ER26-3515-000 · 2026-09-03 · East Kentucky Power Cooperative, Inc.

Limited Protest of East Kentucky Power Cooperative, Inc. to PJM Interconnection, L.L.C.’s 08/13/2026 proposed revisions to the Open Access Transmission…

Text extracted from the eLibrary original (SHA-256 db798fa4f084c525…). Download the original from the official source.

Contents · 19 sections
  1. I. Background p. 2
  2. A. IRAS Overview p. 2
  3. B. The Stakeholder Process and Joint EDC Proposal p. 8
  4. II. Limited Protest p. 9
  5. A. Introduction p. 9
  6. B. Elements of PJM’s IRAS Proposal Are Not Just and Reasonable. p. 14
  7. C. PJM Has Failed to Demonstrate that Compensating IRAS Curtailment Is p. 29
  8. D. PJM’s Proposed Treatment of New Large Loads Served by FRR Entities Is p. 33
  9. E. PJM’s Proposed Revisions to FRR Rules Creates Ambiguity and Disadvantage p. 35
  10. III. Conclusion p. 36
  11. Introduction p. 39
  12. Background p. 41
  13. Discussion p. 48
  14. Conclusion p. 61
  15. I. Introduction p. 65
  16. II. Purpose p. 65
  17. III. EKPC’s LSE Role and Proactive Planning For and Use of Self-Supply Resources p. 66
  18. IV. EKPC’s Data Center Tariff and Obligation To Adjust Power Supply Plan p. 68
  19. V. Conclusion p. 69

Read topic-matched comments in ER26-3515

Topics in the text: Reliability and curtailment · Registry access · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Reliability and curtailment

PJM’s IRAS Proposal includes provisions that are not just and reasonable and could result in the curtailment of load that is supported by capacity resources and therefore not contributing to the resource adequacy concerns that the IRAS Proposal is intended to address.
Read this passage Filed comments: Reliability and curtailment

I. Background

printed heading

I.
Read this passage

A. IRAS Overview

printed heading · Topic match: Registry access

Large Load Registry PJM proposes to establish a centralized registry of Large Loads in the PJM Region, maintained by PJM and updated periodically.19 The registry would collect detailed information including, among other items, peak load quantities, in-service dates, Bring Your Own New Capacity…
Read this passage Filed comments: Registry access

B. The Stakeholder Process and Joint EDC Proposal

printed heading · Topic match: Reliability and curtailment

It is appropriate to place rules upon such entities to mitigate that unreasonable risk to others.”42 The Joint EDC Proposal featured some of the same concepts as PJM’s IRAS Proposal, including a large load registry, a definition of “New Large Load,” and BYONC resources and determinations.43 But,…
Read this passage Filed comments: Reliability and curtailment

II. Limited Protest

printed heading

II.
Read this passage

A. Introduction

printed heading · Topic match: Reliability and curtailment

PJM proposes to determine the zonal allocation of IRAS based on the “total Final RBP Target MW across all zone/areas.”53 Not only does determining the zonal allocation of IRAS pursuant to this proposal fail to account for whether the Large Load included in the forecast used in the RPM Auctions,…
Read this passage Filed comments: Reliability and curtailment

B. Elements of PJM’s IRAS Proposal Are Not Just and Reasonable.

printed heading · Topic match: Reliability and curtailment

However, the requirement that the BYONC resource must be committed in an RPM Capacity Auction in order to be BYONC and thereby reduce IRAS curtailment risk is unreasonably restrictive.
Read this passage Filed comments: Reliability and curtailment

C. PJM Has Failed to Demonstrate that Compensating IRAS Curtailment Is

printed heading · Topic match: Reliability and curtailment

Under PJM’s IRAS Proposal, load reductions provided under IRAS will be compensated at a rate equal to 50% of the applicable Non-Performance Charge Rate.112 Specifically, PJM proposes to “extend the rate applicable for Pre-Emergency Load Response nonperformance (and conversely for bonus payments) –…
Read this passage Filed comments: Reliability and curtailment

D. PJM’s Proposed Treatment of New Large Loads Served by FRR Entities Is

printed heading · Topic match: Reliability and curtailment

If PJM recognizes resource adequacy actions taken under the FRR construct for purposes of avoiding IRAS exposure, principles of comparability require that it similarly recognize owned resources, bilateral contracts, and comparable resource commitments maintained by RPM LSEs when determining IRAS…
Read this passage Filed comments: Reliability and curtailment

E. PJM’s Proposed Revisions to FRR Rules Creates Ambiguity and Disadvantage

printed heading

PJM’s Proposed Revisions to FRR Rules Creates Ambiguity and Disadvantage Entities that May Elect FRR in the Future.
Read this passage

III. Conclusion

printed heading

Foster Cronin Chief Compliance Officer and Senior Vice President East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O.
Read this passage

Introduction

printed heading · Topic match: Reliability and curtailment

IRAS may assign curtailment obligations to Load Serving Entities (“LSEs”) whose loads do not contribute to the resource adequacy deficiency because PJM will propose to link specific resources to specific large loads rather than assess the adequacy of an LSE’s 3 overall resource portfolio.
Read this passage Filed comments: Reliability and curtailment

Background

printed heading · Topic match: Reliability and curtailment

PJM proposes to create and administer a Large Load Registry.5 The registry would contain information on Large Loads, including location, in-service date, peak demand, load-growth schedule, telemetry specifications, backup generation, interconnection status, and capacity arrangements.
Read this passage Filed comments: Reliability and curtailment

Discussion

printed heading · Topic match: Reliability and curtailment

The FRR entity instead must satisfy the resource adequacy requirements associated with that load through its FRR Capacity Plan and supporting resource portfolio, consistent with proposed RAA Schedule 8.1, section D.1.1.
Read this passage Filed comments: Reliability and curtailment

Conclusion

printed heading · Topic match: Reliability and curtailment

As a result, the proposal may shift the consequences of insufficient recognized capacity support, whether in the form of curtailment obligations, compensation costs, or residual reliability risks, to customers and LSEs that did not create the underlying resource adequacy issue.
Read this passage Filed comments: Reliability and curtailment

I. Introduction

printed heading

I am the Vice President of Power Supply and Planning for East Kentucky Power Cooperative, Inc. (“EKPC”).
Read this passage

II. Purpose

printed heading · Topic match: Reliability and curtailment

In doing so, I offer support for the concerns EKPC raised in its Protest of PJM’s proposal to establish an Interim Resource Adequacy Service (“IRAS”).
Read this passage Filed comments: Reliability and curtailment

III. EKPC’s LSE Role and Proactive Planning For and Use of Self-Supply Resources

printed heading · Topic match: Reliability and curtailment

Focusing specifically on the resource adequacy requirements associated with serving our owner members’ load, EKPC has elected to satisfy the RAA obligations by participating in the RPM Capacity Market.
Read this passage Filed comments: Reliability and curtailment

IV. EKPC’s Data Center Tariff and Obligation To Adjust Power Supply Plan

printed heading

EKPC’s Data Center Tariff and Obligation To Adjust Power Supply Plan 17.
Read this passage

V. Conclusion

printed heading

VERIFICATION OF AFFIDAVIT Pursuant to 18 C.F.R. § 385.2005(b)(3), I verify under penalty of perjury that the foregoing Affidavit is true and correct.
Read this passage

Certificate of Service