Motion to Intervene and Comments of Appalachian Voices in support of PJM Interconnection, L.L.C.’s proposed revisions to Reliability Assurance Agreement…
Text extracted from the eLibrary original (SHA-256 18281543087275f4…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in ER26-3515
Topics in the text: Cost allocation · Reliability and curtailment · Registry access
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
By applying only to Load Serving Entities serving New Large Loads, whose size and operational attributes create unique concerns for the bulk transmission system and resource adequacy, PJM’s IRAS Proposal does not unduly discriminate.Read this passage Filed comments: Reliability and curtailment
I. MOTION TO INTERVENE
printed heading
Pursuant to Rule 214 of the Commission’s Rules of Practice and Procedure,3 Appalachian Voices respectfully requests that the Commission grant it full rights associated with party status in this proceeding.Read this passage
II. COMMENTS
printed heading
II.Read this passage
A. The Commission Should Accept PJM’s IRAS Proposal to Help Ensure that New
printed heading · Topic match: Cost allocation
Further, as described below, BRA clearing prices have skyrocketed in recent years due to large load growth, particularly in the DOM zone that covers Dominion’s territory.11 When Dominion does not have sufficient self-supply capacity to serve its native load, that load must pay the BRA prices…Read this passage Filed comments: Cost allocation
B. The IRAS Proposal Reflects an Appropriate Exercise of Jurisdiction under the
printed heading · Topic match: Reliability and curtailment
Although PJM proposes to issue load reduction directives to Electric Distributors, PJM defers to the Electric Distributors and the relevant states to resolve how to prioritize load reductions in their service territories.28 PJM’s IRAS Proposal neither mandates nor prohibits load shed of specific…Read this passage Filed comments: Reliability and curtailment
C. The IRAS Proposal Does Not Unduly Discriminate.
printed heading
PJM’s IRAS Proposal is not unduly discriminatory because any such differentiation among capacity buyers is warranted by the size, operational characteristics, and grid impacts caused by New Large Load.Read this passage
III. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, Appalachian Voices respectfully requests that the Commission approve PJM’s IRAS Proposal.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 3rd day of September 2026. /s/ Nicholas J.Read this passage