ER26-3380-000 · 2026-09-21 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC to the Motion for Leave to Answer and Answer of PJM Interconnection, L.L.C.…

Text extracted from the eLibrary original (SHA-256 8054375f937de2a0…). Download the original from the official source.

Contents · 6 sections
  1. I. BACKGROUND p. 1
  2. II. ANSWER p. 2
  3. A. Eddystone and Similarly Situated Energy Resources Should Qualify as RBP p. 2
  4. B. PJM Mischaracterizes the Commission’s Treatment of Price Taker p. 4
  5. C. Constellation Supports PJM’s Suggestion to Sever Credit and Collateral p. 9
  6. III. CONCLUSION p. 10

Read topic-matched comments in ER26-3380

Topics in the text: Reliability and curtailment · Credit and exit · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C. ) Docket No.
Read this passage

I. BACKGROUND

printed heading · Topic match: Reliability and curtailment

PJM Interconnection LLC, 98 FERC ¶ 61,208, at p. 61,756 (2002) (answer accepted to provide new factual and legal material to assist the Commission in decision-making process). 4 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large…
Read this passage Filed comments: Reliability and curtailment

II. ANSWER

printed heading

II.
Read this passage

A. Eddystone and Similarly Situated Energy Resources Should Qualify as RBP

printed heading · Topic match: Cost allocation

The Secretary has extended its 202(c) order for Eddystone continuously since, most recently on August 21, 2026.9 Notably, those DOE orders direct that the Eddystone units “shall not be considered capacity resources.”10 As a result, Constellation requested, and the Commission granted, a request for…
Read this passage Filed comments: Cost allocation

B. PJM Mischaracterizes the Commission’s Treatment of Price Taker

printed heading · Topic match: Reliability and curtailment

Power 8 price takers in each RPM for up to 15 years—again resulting in outsized impact on markets, resource adequacy and costs—a duration far greater than what was contemplated in the RMR proceedings. • The Commission Must Consider the Cumulative Effect of PJM’s Out-of-Market Interventions.
Read this passage Filed comments: Reliability and curtailment

C. Constellation Supports PJM’s Suggestion to Sever Credit and Collateral

printed heading · Topic match: Credit and exit

Constellation Supports PJM’s Suggestion to Sever Credit and Collateral Issues Constellation and others raised concerns about the load serving entity (“LSE”) collateral and credit requirements in the PJM Proposal.26 In the PJM Answer, PJM acknowledged that “reasonable minds may differ on the credit…
Read this passage Filed comments: Credit and exit

III. CONCLUSION

printed heading

CONCLUSION In accordance with PJM’s willingness to accept changes under NRG Power Marketing,30 the Commission should (i) accept the RBP subject to the modifications Constellation discussed in its Limited Protest and Answer, as clarified herein, and (ii) sever the LSE credit issue discussed in its…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 21st day of September 2026. /s/ Alexandra K.