Clinch River · BWRX-300

TVA's utility-led BWRX-300 project at the already permitted Clinch River site.

Oak Ridge, Tennessee · Government-reported

Lead company · Tennessee Valley Authority

Program · Gen III+ SMR Pathway · NRC construction-permit review

Construction-permit reviewHigh confidence
Deployment stage3 / 8Development

Deployment trajectory

1Interest
2Preliminary
3Development
4Contractual
5Ready
6Physical
7Operational
8Replication

Latest milestone

NRC accepted TVA's construction-permit application for a full safety review.

2025-07 · DOE summary of NRC docketing

Open primary source ↗

Next milestone

Complete NRC safety review and obtain the construction permit before nuclear construction.

Responsible
TVA and NRC
Key blocker
Construction-permit decision, final design, supply chain, and project finance
GenerationGen III+
ScaleSMR
Reactor familyLWR · BWR
RoleCommercial power
Capacity300 MWe
Reporting basisGovernment-reported