Federal action

Four executive orders and DOE programs, with owners, deadlines, current status, and next actions.

Executive orders

EO 14299In progress

National security deployment

Operate an Army-regulated reactor at a domestic military installation by September 30, 2028.

Owner
Department of Defense / Army
Next step
Select vendors and match designs to the nine candidate installations
Read executive order ↗
EO 14300Implementation underway

NRC reform

Revise NRC rules and establish fixed licensing deadlines, including an 18-month ceiling for new-reactor decisions.

Owner
Nuclear Regulatory Commission
Next step
Rules and guidance
Read executive order ↗
EO 14301Goal exceeded · DOE reported four criticalities

DOE reactor testing

Create a pilot pathway for reactors outside national laboratories, targeting at least three criticalities by July 4, 2026.

Owner
Department of Energy
Next step
Operational validation and commercialization
Read executive order ↗
EO 14302In progress

Industrial base

Expand fuel availability, domestic supply chains, workforce, financing, and large-reactor deployment capacity.

Owner
DOE and partner agencies
Next step
Convert conditional support into closed, delivered projects
Read executive order ↗

DOE deployment programs

01

Reactor Pilot Program

DOE authorization for privately funded test reactors outside national laboratories.

MEASURE11 initial projects; at least 3 targeted criticalities by July 4, 2026
STATUSFour DOE-reported criticalities tracked across the Pilot Program and Launch Pad
SOURCE ↗
02

Advanced Reactor Demonstration Program

Cost-shared commercial demonstrations of Natrium and Xe-100 technologies.

MEASURE$3.2B planned federal investment over seven years, subject to appropriations, with matching industry funds
STATUSNatrium permitted and under construction; Long Mott license review active
SOURCE ↗
03

DOME

A test bed for fueled microreactor experiments.

MEASURETwo initial conditional test selections
STATUSFacility opened in April 2026
SOURCE ↗
04

Nuclear Energy Launch Pad

DOE-authorized reactor experiments at national-laboratory sites.

MEASUREFirst tracked experiment: Deployable Energy Unity
STATUSUnity achieved DOE-reported initial criticality on June 30, 2026
SOURCE ↗